Florida Power and Light'
'Assessment 79% complete, renovation 17% complete
Replace
Applications being replaced to improve functionality will include Year 2000 compliance in design and development Examples:Trouble Call Management System, Revenue Facilities Management System, General Accounting.
Renovate
By outsourcing to service providers/consultants/experts, corporate systems staff, local business unit staff, or vendors of application software Procurement systems, inter-utility billing systems, some financial systems, load management system Customer information and billing system Power plant maintenance systems in both nuclear and fossil generation business units Payroll system, Inventory systems
Retire
Remove applications no longer used
Expect to complete in 1998 except for some replacements carrying into 1999 _____
Embedded systems:
' Assessment 14% complete, renovation 1% complete
Methodology
Generate inventory from internal systems and walkdowns In parallel, obtain Y2K statements from vendors Match inventory to vendor statements For Y2K compliant, prepare/execute test plan For Y2K non-compliant, prepare/execute plan to fix and test
Selectively use service providers/consultants/experts to assist
Power plant inventories and system component testing Assessment for power delivery, distribution and telecommunication Nuclear embedded system component testing
Renovation work dependent on outages will continue into 1999