We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : KERM'S KORNER

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: Kerm Yerman who wrote (11259)6/16/1998 8:18:00 PM
From: Herb Duncan  Read Replies (1) of 15196
 
FIELD ACTIVITIES / Diaz Announces the Commencement of Drilling
Operations in Louisiana

VSE SYMBOL: DZR.A DZR.B
NASDAQ SYMBOL: DZRUF

JUNE 16, 1998



CALGARY, ALBERTA--Diaz Resources Ltd. announces that drilling
operations have begun on the No. 1 Miami Corporation well in
section 22, T13S-R5W, Cameron Parish, Louisiana, on its South
Lakeside prospect. The South Lakeside prospect is an exploratory
natural gas and condensate drilling project with a primary
objective of the Miogypsonoide (MioGyp) gas charged sands at an
approximate depth of 17,350 feet. Diaz will be carried through
the cost of the re-entry and completion of the well and will have
a 5.75 percent working interest thereafter in the 2,313 acre
prospect.

The South Lakeside prospect involves re-entering the No. 1 Miami
well drilled by CMS-Nomeco to a depth of 17,490 feet in 1997. The
original objective of the well was a large reserve target in the
MioGyp sands based upon 2D seismic and a down-dip well drilled by
Arco 2.4 miles to the west in section 30, T13S-R5W, which had
several hundred feet of MioGyp sands with gas shows. The No. 1
Miami well encountered strong gas shows at the MioGyp target depth
and is interpreted to have drilling into the up-dip edge of the
reservoir. Operations commenced on June 10th to re-enter the well
and to drill a side track out from existing casing at 13,450 feet
to intersect the MioGyp reservoir target at a structurally
down-dip position to the west of the original wellbore. Drilling
operations reported presently to be at a depth of 7,000 feet. The
operation is expected to take 40-60 days.