We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : Laverton Gold VSE:LAV

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: Morgan R. Naidoo who wrote (2)11/29/1996 3:40:00 PM
From: burner   of 45
 
Morgan, Latest NEWS RELEASE:

Rawas gold project

Laverton Gold N.L. LAV
Shares issued 103,997,383 Nov 28 close $0.42
Fri 29 Nov 96 News Release
Mr Jim Williams reports
The project construction is now 85% complete and Minproc is anticipating
December 30 as the date when ore will go into the circuit. Any change in
this date will be in the order of days, not weeks.
The weather continues to be kind (dry) which, to a degree, compensates for
March, April and May.
The sag mill has been installed and steel liners are currently being
installed. The Morgardshammar mill is 5m in diameter and 6.1m long and is
driven by a 2.3 mw motor which will draw 1.6 mw.
Stage I tailings dam has been constructed to accommodate the tailings for
the first 18 months. It will be increased in height in the middle of 1997.
In the foreground are containers each containing either 0.75 mw or 1.25 mw
generators. The raft in the tailings dam holds the pumps which supply
decant water to the process plant.