We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : KERM'S KORNER

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: Kerm Yerman who wrote (11669)7/11/1998 7:54:00 AM
From: Kerm Yerman  Read Replies (1) of 15196
 
MEDIA RELEASE / Sable Offshore Energy Inc Site Work Commences

SITE WORK BEGINS FOR NATURAL GAS LIQUIDS PROCESSING FACILITY - SABLE
OFFSHORE ENERGY INCORPORATED

PORT HAWKESBURY, N.S., July 10 /CNW/ - Sable Offshore Energy Incorporated
(SOE Inc) contractors started site clearing work this week in preparation for
the natural gas liquids (NGL) processing facility at the Point Tupper
Industrial Area located near this Cape Breton community. The new site has been
leased from Statia Terminals Canada Inc.

J & T Van Zutphen of Port Hood will employ about 40 people over the next
four months on the clearing, earthworks and site preparation for the natural
gas liquids (NGLs) fractionation plant, propane and butane storage and truck
and rail loading facilities on part of the 36 hectare site.

The facility is expected to cost about $50 million, excluding pipelines.

The Sable Offshore Energy Project Facilities Alliance onshore
construction manager, BBA, A Joint Venture, (BMS Offshore, Brown & Root, Agra
Monenco) awarded the site work contract. In the next few weeks BBA will award
several contracts for the construction of the fractionation plant and
associated facilities which have been designed by the Halifax-based group of
consultants ACCENT Engineering.

BBA Project Manager Steve Corkum expects foundation work to begin in late
August with steel and pipe erection beginning in September. Equipment and
plant components will probably begin moving on to the site in October.

Peak employment at Point Tupper will occur in December when approximately
150 trades people will be involved in the construction activities.

Corkum said that mechanical completion of the plant is expected in May
1999 when plant commissioning will begin and continue through to November
1999.

The Point Tupper fractionation plant will process an average about 20,000
barrels a day of natural gas liquids which will be delivered to the plant by
pipeline from the Goldboro Gas Processing Plant in Guysborough County.

While NGL volumes will vary according to field source and production
rates, the Point Tupper plant is expected to produce about 10,500 barrels a
day of condensate (light oil), 6250 barrels a day of propane, and about 3250
barrels a day of butane.