We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : Tusk Energy (TKE)

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: frankl who wrote (857)9/16/1998 1:31:00 PM
From: grayhairs  Read Replies (2) of 1207
 
Thanks Frank.

Let's not forget that:

A production rate of 5 MMCF/d would yield annual production of 1.825 BCF and in 20 years would drain 36.5 BCF.

A production rate of 10 MMCF/d would yield annual production of 3.650 BCF and in 20 years would drain 73.0 BCF.

A production rate of 15 MMCF/d would yield annual production of 5.475 BCF and in 20 years would drain 109.5 BCF.

Anything in the 10 MMCF/d range will be a very nice well, to be sure!!

Later,
grayhairs