We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : KERM'S KORNER

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: Kerm Yerman who wrote (13422)11/11/1998 4:48:00 AM
From: Kerm Yerman  Read Replies (5) of 15196
 
REPORT / Canada Refinery Maintenance (updates Vitol)

CALGARY, Oct 5 (Reuters) - The following list details
1998 maintenance schedules, repairs, outages, etc. at Canadian
refineries.

The list is compiled on a "best efforts" basis using
market sources where the company does not confirm and may not
be definitive. (*confirmed by company)

COMPANY LOCATION REFINERY DETAILS CAPACITY
--------------------------------------------------------------
IMPERIAL* SARNIA ON NO PLANNED SHUTDOWNS FOR 119,000
Q4 1998
IMPERIAL* NANTICOKE ON NO PLANNED SHUTDOWNS FOR 112,000
Q4 1998
IMPERIAL* DARTMOUTH NS NO PLANNED SHUTDOWNS FOR 82,000
Q4 1998
IMPERIAL* EDMONTON AB NO PLANNED SHUTDOWNS FOR 176,000
Q4 1998. LAST OUTAGE WAS
IN Q2 1998, WHEN
ALKYLIZATION UNIT, HYDRO
TREATER, ATMOSPHERIC &
VACCUUM UNIT AND
POWERFORMER DOWN. CAT
CRACKER REMAINED IN
OPERATION
PETROCAN* EDMONTON AB PLATFORMER, REFORMER, CRUDE 116,000
UNIT, COKER, CAT CRACKER,
ALKYLIZATION UNIT PLANNED
TO BE DOWN IN Q2, 1998
PETROCAN* MONTREAL QU NO. 1 CRUDE UNIT, POWER- 87,000
FORMER, PLATFORMER, ISOMAX,
VISBREAKER, CANMET UNIT
DOWN Q2 1998. CAT CRACKER,
POLYMERIZATION UNIT,
ALKYLIZATION UNIT PLANNED
DOWN Q3 1998. POWER OUTAGE
CAUSED 3-DAY SHUTDOWN JAN.
9-11, '98.
PETROCAN* OAKVILLE ON REFORMER PLANNED DOWN Q3 1998 81,000
SHELL* FT SASK. AB FULL PLANT OUTAGE FOR 15 DAYS 90,000
IN Q2, 1998.
SHELL* MONTREAL QU SOME MAINTENANCE PLANNED 130,000
FOR Q4 1998. POWER OUTAGE
CAUSED SHUTDOWN JAN. 9-10,
1998.
SHELL* SARNIA ON FIRE TO HYDROCRACKER 72,000
HEATER SEPT. 28 CUT RUNS
TO 50,000 BPD. ROSE TO
63,000 BY OCT. 5.
CHEVRON* BURNABY BC NO MAJOR TURNAROUNDS PLANNED. 50,000
INSTALLING PENEX UNIT AND
ADAPTING PLANT TO MEET NEW
B.C. REFORMULATED FUEL
REGULATIONS ON SULPHUR AND
BENZENE CONTENT FOR Q4 1998
SUNCOR* SARNIA ON NO MAJOR TURNAROUNDS PLANNED 70,000
IN 1998.
SUNCOR* FT MCMURRAY AB (OIL SANDS PLANT) MAJOR 85,000
TURNAROUND AND DEBOTTLE-
NECKING WAS IN Q2 1997.
BOOSTED CAPACITY. NOTHING
MAJOR PLANNED IN 1998.
SYNCRUDE* FT MCMURRAY AB (OIL SANDS PLANT) RESTARTED 220,000
COKER UNIT AUG. 19 AFTER
26-DAY SHUTDOWN TO REPAIR
REACTOR UNIT. AVERAGE 1998
PRODUCTION FORECAST NOW AT
212,000, DOWN FROM PREVIOUS
ESTIMATE OF 230,000.
HUSKY OIL *LLOYDMIN. AB (HEAVY OIL UPGRADER) PLANS TO 54,000
BOOST UPGRADER CAPACITY TO
150,000 BPD SYNTHETIC OIL
AND PRODUCTS WITH C$500 MLN
PROJECT. ESTIMATED ON
STREAM IN 2001 WITH
CONSTRUCTION START PLANNED
IN SECOND HALF 1999.
CONSUMERS' CO-OPERATIVE(HEAVY OIL UPGRADER) 52,000
REGINA SK
ULTRAMAR ST ROMUALD QU 150,000
IRVING* ST. JOHN, NB FIRE TO 34,600 BPD HYDRO- 250,000
CRACKER CUTPRODUCTION BY
20,000 BPD JUNE 9. OTHER
UNITS OPERATED NORMALLY.
NORTH ATLANTIC REFINING* ROUTINE MAINTENANCE SET FOR 105,000
(VITOL) COME BY CHANCE, SECOND HALF OF OCTOBER,
NF LIKELY FOR TWOWEEKS. EXACT
DATES, OUTPUT UNDISCLOSED.
MARCH 25,1998. THREE-WEEK
SCHEDULED MAINTENANCE WORK
MOVED UP IN CONJUNCTION
WITH REPAIRS TO THE UNIT.
FULL SHUTDOWN CONTINUED
UNTIL 3RD WEEK IN APRIL,
1998.