SouthernEra Resources Limited
- Phase 1 of the Leopard Fissure Mining Commences - 50 tph DMS Treatment Plant Ordered - Exploration Budget Approved by Marsfontein Joint Venture - October 1998 Results at Marsfontein and Angola - Additional Diamondiferous Gravels on the Farm Marsfontein
TORONTO, Nov. 12 /CNW/ -
SOUTH AFRICA ------------
Klipspringer
SouthernEra Resources Limited (SUF-TSE) today announced that development of the Phase 1 underground project has commenced on the Leopard Fissure at the Klipspringer Project (100% SUF) in the Northern Province of South Africa. The Phase 1 underground project will mine the upper 100 metres of the eastern section of the Leopard Fissure (Ingwe section) via adits along a strike length of 1.8km over a period of 29 months. A 50 tph DMS plant has been ordered and is expected to be built beside the existing 100 tph plant and completed by the end of March 1999. At that time, fissure ground will be treated and by mid 1999, a production rate of 12,000 tpm should be achieved. The new 50 tph plant will also allow exploration bulk samples to be treated independently of the Marsfontein 100 tph plant. The recovered grade of the Leopard fissure is expected to be 70 carats per hundred tonnes treated. A previous parcel of 4,832 carats of Leopard fissure diamonds was sold in 1997 for a gross US $126/carat. By the end of 1999, the top 100m of the western section of the Leopard fissure (Ndau section) will be mined in a similar manner. Underhand shrinkage stoping will be used at the Ingwe section. The Ingwe section is estimated to contain 450,000 tonnes while the Ndau section is estimated to contain 750,000 tonnes. During the mining of the Ingwe and Ndau sections, a feasibility study will be completed in order to commence the deeper mining of the Leopard fissure. The capital cost of the 50 tph DMS plant is Cdn. $2.34 million.
Marsfontein -----------
It has been agreed by the Joint Venture partners (60% De Beers, 40% SUF) that Cdn. $763,000 will be spent on an initial exploration program on the farm Marsfontein. Many anomalies remain to be explored which may require follow-up drilling. In addition, the waste stripping at the M1 pipe has shown the existence of extensive diamondiferous gravel horizons to the south and southeast of the M1 pipe. Those gravels falling within the stripping perimeter of the M1 pipe have been stockpiled for future treatment. Further delineation and grade determination of these gravels will be completed in the future exploration program. In October 1998 the Marsfontein Joint Venture produced 144,882 carats from 26,531 tonnes treated comprising a combination of overburden, weathered kimberlite and some diabase with kimberlite stringers. The diabase was encountered during the waste stripping and was treated to facilitate a greater throughput in the plant which has been slowed due to excessive amounts of fines (less than 1mm) in the overburden and weathered kimberlite. Since the start of commercial production on 31 August 1998, the M1 pipe has produced over 359,000 carats from 57,873 tonnes treated for a recovered grade of 621 cpht. In addition, over 25,000 carats were produced from bulk sampling in August. Gross revenue has averaged US $191 per carat on sales to-date. The current overburden and weathered kimberlite stockpile is expected to be exhausted by late November. Thereafter, a combination of weathered and primary kimberlite will be mined and treated for some months.
ANGOLA ------
Luo ---
At Luo, 1,507 carats were produced in October 1998. The new river diversion has allowed access to the original riverbed, but large amounts of water have to be pumped out before the gravels above the bedrock can be accessed. To the end of October 1998, 25,800 carats have been produced at an average gross sale value of US $191 per carat.
Cassanguidi -----------
At Cassanguidi, 42,211 carats were produced in October 1998, but rain may diminish production during the rainy months ahead. Total production in 1998 to the end of October from Cassanguidi is 107,200 carats at an average gross value of US$ 114 per carat.
Camafuca --------
Trenching for bulk sampling continues at Camafuca and the pan plant is being assembled. It is expected to start treating material in December.
SouthernEra has implemented additional security measures in Angola and is monitoring the current situation very carefully.
%SEDAR: 00004535E
-30-
For further information: Christopher M.H. Jennings, President; A. Lee Barker, Senior Vice President; Kim Freeman, Vice-President, Operations; Frank van de Water, Vice President, Finance; Nicholas Sayce, Investor Relations; Phone: (416) 359-9282; Fax: (416) 359-9141; e-mail: inbox@southernera.com; southernera.com
|