SI
SI
discoversearch

We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : ABER RESOURCES

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
To: Bob Fairchild who wrote (963)1/22/1999 4:19:00 PM
From: don jackson  Read Replies (1) of 2006
 
Aber Resources Ltd. announces Diavik Diamonds Project update

VANCOUVER, Jan. 22 /CNW/ - ABER RESOURCES LTD. (TSE-ABZ, NASDAQ-ABERF)
announces that project manager, Diavik Diamond Mines Inc. (''DDMI''), will
file supplemental information to the Project Description with the Canadian
Federal Government today. The filing will update work completed thus far on
the Diavik Diamonds Project feasibility study and Environmental Assessment.
DDMI and Nishi-Khon SNC Lavalin (''SNC''), the engineering firm completing the
feasibility study, have identified some components of the proposed project
that can be refined. These changes do not affect the overall results of the
Environmental Assessment.
The ongoing feasibility study engineering has determined that the water
retention dikes required to open pit mine the Diavik reserves could be
constructed more efficiently than previously envisioned while still meeting
the Canadian Dam Safety regulations. The refined dike construction method
reduces the overall footprint and construction material requirements with a
resulting reduction in equipment requirements, fuel and construction time.
Most importantly, this construction method will allow earlier access to the
larger portion of the project's overall reserves in the A-154S and A-154N
kimberlite pipes.
The feasibility study and the environmental assessment are proceeding as
planned. The feasibility study is currently expected to be completed early in
the second quarter of 1999. Estimates of costs, based on the increased level
of detailed engineering work in the feasibility study, are not complete. The
estimated capital and operating costs and the revised mining plan for the
project will be available with the conclusion of the feasibility study.
The proposed mine development plan now includes construction of the A-154
dike in the years 2000 and 2001. Open pit mining on the A-154 pipes would
begin in the second quarter of 2002 and would continue for ten years. The
A-418 dike would be constructed in approximately 2007. In the previous plan
A-418 would have been mined first.
In the revised mining plan, the A-21 pit would be mined over a three-year
period from approximately 2012 to 2014. This compares with a period from 2012
to 2025 for mining the A-21 pit in the previous mine plan. The four million
tonnes of ore from A-21 will be placed in the process plant area stockpile and
will slowly be fed to the plant over the three-year open pit life and the
following five-year period. This approach allows for a more efficient
transition to an underground mining operation. Mine life projections remain
unchanged.
The feasibility study includes a range of production rates from 1.5 to
1.9 million tonnes per year. In the revised mine plan the estimated tonnage
of mined kimberlite ore remains unchanged at approximately 26 million tonnes.
Exploration for additional resources outside of the mine plan on the Diavik
Diamonds Project is continuing with an anticipated budget of $2.8M which
includes the drilling of two diamondiferous kimberlite pipes.
Aber has a 40% interest in the Diavik Diamonds Project and retains the
right to market its 40% share of diamond production. The remaining 60% is
owned by Yellowknife-based DDMI, a subsidiary of Rio Tinto plc of London.
Report TOU ViolationShare This Post
 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext