Uh oh, ABTE gets strangled by Dizard/The Post: "PASS-ING THE BUCK: Installation of the E-ZPass system is a year behind schedule on New Jersey roads including the Garden State Parkway. FAILING GRADE FOR E-ZPASS IN N.J. By JOHN DIZARD
Regional transportation experts and Wall Streeters said they doubt the current contract to implement E-ZPass on the New Jersey Turnpike and other area toll roads can be completed, The Post has learned.
The pessimism surrounding the automatic toll collection system comes after MFS Network Technologies, the prime contractor for the E-ZPass system, failed last week to meet a key construction deadline and has stumbled through several management changes.
As a result, drivers in the state, which has the densest automobile registration of any state, can look forward to continued long lines at toll booths and longer commutes.
E-ZPass was supposed to be up and running by early 2000 but the delay will push that date back by at least a year.
A subcontractor which had worked with MFSNT, a unit of publicly-traded Able Telecom Holdings, has accused the company of nonpayment and failure to deliver key components.
MFSNT has denied all accusations and said its E-ZPass work was on the road to completion.
Despite the delay in completing the project, the executive director of the New Jersey Turnpike Authority, Edward Gross, said he and his colleagues in the consortium for the New Jersey and Delaware E-ZPass system have decided to keep MSFNT on the job.
At least one lawmaker thinks that's a mistake.
"This is not so 'E-ZPass,'" says N.J. Assembly Minority Leader Richard Codey. "We want the state auditor to examine this contract. They should send this company packing on the Turnpike. Obviously, what has happened to date is indicative of the incompetence of the company. We're better off starting all over again."
Wall Street short-sellers are even harsher in their condemnation of Able Telecom, MFSNT's corporate parent, and of Gross.
"Ed Gross has put the E-ZPass consortium at risk by keeping Able on the job," says Manuel Asensio of Asensio & Co., which has a short position in the stock. "The bonding underwriters can refuse to pay if MFSNT defaults because [Gross] is not performing the required due diligence."
Short-sellers such as Asensio profit if Able's stock declines because of problems with E-ZPass, which represents much of the company's projected revenues.
In addition, a senior technical official with a large New York-area transportation agency claims "MFSNT is well behind in getting the critical lane controller and violation processing software together. We're talking double-digit months. The target was the beginning of 2000, and that is completely unrealistic."
The entire E-ZPass implementation has turned into a morass of legal and non-legal disputes, delays, management and technical staff turnover.
Able Telecom bought MFSNT from telecom giant MCI-Worldcom last year. Able was not able to post the necessary $200 million performance bond for the giant E-ZPass contract; MCI Worldcom had to put up the guarantee for Able's completion of the project.
Since the sale, Able has had to go back to MCI Worldcom for cash advances to finance its operations and to buy back a securities issue that was on the verge of default.
Yesterday, Able shares closed at 67/16, up 1/16, which is well below its 52-week high of 205/16.
A spokesman for Able told The Post that the company was innocent of the accusations leveled against it.
In addition, the company said: "Our Violation Processing Center is along the path to working and is in the testing processs."
Furthermore, it claims it has more than sufficient working capital to complete the project.
So far, of the total $234 million actually budgeted for the project, less than $23 million has gone out in progress payments.
newyorkpost.com |