NEWS RELEASE
May 18, 1999 VSE-EMG Sedar Profile #00003879
The Board of Directors is pleased to provide this update:
SANTA ROSA PROJECT
The plans to proceed with project finances and on to production have been advanced this week.
The data in hand are sufficient to allow El Misti Gold Limited to proceed initially on the oxide zones at Santa Rosa.
With the low cost metal production (gold and silver) and the low estimated capital cost, the Board is taking an accelerated path through project finance to allow project initiation. Sufficient resources have been outlined to sustain 400 days at 3,240 tonnes per day mining rate. When the feasibility study is signed off, full details will be published. Project finances will dictate the start date. If finances can be drawn down early, project long lead items can be purchased earlier and save significant time. Current scheduled key dates are:
Complete Piping & Instrumentation Drawings & Civil Engineering June 30, 1999 Completion of Feasibility July 20, 1999 Place Crusher Order September 30, 1999 Commission Project February 28, 2000 Project Complete March 31, 2000
SAND DOS - Update
The Sand Dos project as announced December 16, 1998 is being placed into production by Roca Fuerte S.A. El Misti Gold S.A. receives a 7% NSR for all metal and mineral production. The production rate is 10,000 TPD according to the agreement between El Misti Gold S.A. and Roca Fuerte S.A. Roca Fuerte have advised they believe sufficient material exists to allow a minimum of 5 years production at the contract rate. Roca Fuerte have requested a 60 day inclement weather extension to initiate production.
Production at 5,000 TPD is now scheduled to begin in early July. An increase to 10,000 TPD will follow two months thereafter.
For further information, please contact John Huguet or Marie Antoinette Shields - Market Finance Development. Phone: (604) 681-6186 Direct Fax : (604) 681-3652 Web site : www.elmisti.com
On behalf of the Board,
"John Huguet" John Huguet Chairman & CEO
This news release may contain forward-looking statements regarding upcoming work programs and actual results may differ materially from those currently anticipated in such statements.
The Vancouver Stock Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of this news release |