We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Politics : Formerly About Advanced Micro Devices -- Ignore unavailable to you. Want to Upgrade?


To: tejek who wrote (82632)12/10/1999 9:50:00 PM
From: Shane Geary  Respond to of 1572108
 
Ted - Re:"what is a reasonable period of time?"

The fastest I've heard a fab to go from ground-breaking to production was about 9-10 months if I recall correctly. That seems incredibly fast to me - in my experience 18 months is more typical.

However, this relies on a process being TRANSFERRED to the fab.

A new process generation is likely to take 2 years from initial planning to volume production.

So, it depends how much work AMD had/has to do to Motorola's HiP6L process. I can't answer that question apart from note that HiP6L is in production already in Motorola's fabs.

My own feeling is that AMD do not require wafers from Fab 30 for a while yet and that they could certainly put out about 500-1000 wafers/week if they DID need to.

AMD don't need Fab 30 right now because:

(i) Fab 25 more than satisfied Athlon demand in Q3
(ii) Fab 25 was only running at 80% of rated ouput at that time (had a spare 1000 wfrs/week)
(iii) That was on a 0.25um process. All wafer starts are on 0.18um now giving twice the die/wafer.

On the other hand, Athlon demand should start exceeding Fab 25 capacity in Q1 or Q2 - when Dresden will come on line.

So, in my opinion, Dresden is waiting for the demand, not the other way around.