We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : Precious and Base Metal Investing -- Ignore unavailable to you. Want to Upgrade?


To: marynell who wrote (280)10/23/2001 10:25:05 AM
From: Claude Cormier  Read Replies (1) | Respond to of 39344
 
Marynell,

Although the final numbers will be in only in the next quarter Corner Bay current mining plan is as follows:

Year 1 & 2: 17.5+ million ounces of silver equivalent per year at a cash cost near $1.50

Year 3 - 5: 8.5+ million ounces of silver equivalent per year at a cash cost near $3.00

To answer your question, In year 1 and 2, it would be near $1.85-$2.00, in year 3-5 it would be near $3.40+

Beyond year 5, BAY nead $5 assuming that no other reserves are developed and the mining plan doesn't change. But given the existence of a high grade feeder zone that will be explore and develop in later years, it make no sense to speculate beyond those first 5 years.

LOM cash cost are currently estimated at $3.00/oz.

Keep in mind that the recently announced higher recovery rates as well as the currently lower silver prices will likely change these numbers.