Russ,
What is your take on the Gabriel news?
Gabriel completes basic engineering phase for Rosia Montana Gabriel Resources Ltd (2) GBU Shares issued 113,552,669 Feb 25 close $3.95 Tue 25 Feb 2003 News Release Mr. Simon Lawrence reports PROJECT UPDATE - ROSIA MONTANA Gabriel Resources has provided further information on the development of its 80-per-cent-owned Rosia Montana gold project in Romania. Highlights The basic engineering phase of development has been completed. Total cash costs of $115 (U.S.) per ounce are in the lowest quartile during the initial five years of mine life. An updated financial analysis confirms strong project economics. A total of 20 per cent of local Rosia Montana residents have entered into legal purchase agreements. A village relocation program will be accelerated. The company has received a key archaeological discharge certificate. Romania has enacted EU compliant environmental laws. Rosia Montana's EIA is scheduled for approval prior to the end of 2003. The basic engineering phase of development has been completed. Overview and scope of the SNC study SNC Lavalin Engineers & Constructors Inc. was engaged by Gabriel in October, 2001, to undertake the basic engineering phase of development of the project in order to produce a control estimate sufficient to provide the basis for the detailed engineering and preconstruction phases of development; to engineer and cost additional items identified in the feasibility study of August, 2001; as well as to support project debt financing of the project. SNC has now completed the basic engineering and has delivered the control estimate, incorporating updated capital and operating costs, to Gabriel. The basic engineering was originally scheduled for completion during the fourth quarter of 2002. Completion was postponed as a result of the new senior technical management team hired by Gabriel in July, 2002, making a series of changes to the original scope of work in order to improve the accuracy of the control estimate and to optimize a number of technical and environmental aspects of the project. The additional time has enabled Gabriel to complete additional work to enhance several aspects of the project. The level of engineering completed during basic engineering represents approximately 25 per cent to 30 per cent of the detailed engineering ultimately required. Updated financial analysis A summary of the updated project economics prepared by Gabriel, incorporating the control estimate prepared by SNC, on a 100-per-cent-project basis, a nominal 13 Mtpa plant throughput and assuming owner mining, is set forth below. Dollar figures are in millions of dollars. Plant throughput: 13.3 Mtpa Reserves: 10.6 million ounces gold, 52.3 million ounces silver Mine life: 16.4 years Average annual gold initial 60 months, 679,000; life of mine, 533,000 Initial capital cost$437 Working capital: $16 Sustaining capital: $123
Initial Life 60 months of mine
Cash operating costs $107 $144
Total cash costs 115 152
Total production costs 174 221
GOLD PRICE
$300 $350 $400 (U.S.) (U.S.) (U.S.)
Internal rate of return 14.6 20.4 25.5
Net present value (0 per cent) 622 970 1,319
Net present value (5 per cent) 273 483 693
Payback period (years) 3.9 3.0 2.6
Gabriel continues to review the option of using contract mining. An initial evaluation of this option indicates potential cost savings of $53-million (U.S.) in initial capital and $50-million (U.S.) in sustaining capital costs. Resources, updated estimate During 2002, Gabriel undertook an infill and grade-control drill program consisting of 21,457 metres of reverse circulation drilling in 247 holes to further delineate and upgrade the resource within the proposed pits for the initial seven years of mining. This program was designed and supervised by RSG Global of Perth, Western Australia. Upon completion of the program, RSG prepared an updated resource estimate. Using a 0.6-gram-per-tonne gold cutoff, a 20-by-20-by-10-metre block size and ordinary kriging, the updated resource estimate is set forth below.
Category of Grade (g/t) resource Tonnes gold silver
Measured 135,253,000 1.58 8.7
Indicated 171,492,000 1.13 4.6 ----------- ---- --- Total M and I: 306,745,000 1.33 6.4
Inferred 52,936,000 0.99 3.7
Category of Contained ounces resource gold silver
Measured 6,900,000 37,800,000
Indicated 6,200,000 25,400,000 ----------- ---------- Total M and I: 13,100,000 63,200,000
Inferred 1,700,000 6,200,000
Independent resource audit Upon completion of the updated resource estimate, Gabriel engaged Independent Mining Consultants Inc. of Tucson, to conduct an independent audit of the resource estimate in order to confirm the resource model for the project. IMC undertook a review of grade interpolation, resource classification and constraints on high-grade samples, as well as all QA/QC procedures, among other matters. IMC concluded that the procedures adopted by RSG to construct the resource model and prepare the resource estimate were reasonable and represented an accurate assessment of the resource. Reserves, updated estimate Upon satisfactory completion of the independent resource audit, Gabriel engaged IMC to prepare an updated reserve estimate and a new mine plan. Using a variable 0.6-gram-per-tonne-gold-cutoff-grade strategy, from 0.62 gram per tonne to 0.94 gram per tonne, and a $300 (U.S.) gold price and a $4.50 (U.S.) silver price, the updated proven and probable reserve estimate is set forth below.
PROVEN AND PROBABLE RESERVES
Grade (g/t) Category Tonnes gold silver
Proven 110,398,000 1.76 9.5
Probable 107,557,000 1.27 5.4 ----------- ---- --- Total 217,955,000 1.52 7.5
In situ metal (oz) Category gold silver
Proven 6,200,000 33,800,000
Probable 4,400,000 18,500,000 ---------- ---------- Total 10,600,000 52,300,000
Exploration potential The deposits at Rosia Montana have not yet been fully delineated and remain open in three directions and at depth. Significant gold mineralization also exists on the Bucium property, immediately to the southeast of and contiguous with Rosia Montana. A number of areas of existing inferred resources at Rosia Montana remain to be upgraded and a number of areas remain to be tested for the existence of additional resources, including areas to the north of the valley, east of Cirnic, to both the east and west of Orlea, between Orlea and Carpeni, to the south at Howie, as well as at depth. These areas are identified on various maps on Gabriel's Web site at www.gabrielresources.com. Delineation of additional resources, and their upgrading to reserves, would provide the potential to extend the current mine life of the project. Mine plan IMC prepared an updated and optimized mine plan which indicates a slight increase in overall tonnage, an increase in contained ounces, an increase in gold grades during the initial four years of production and an increase in the waste-to-ore strip ratio from 0.9:1 to 1.2:1 over the life of the mine. The preproduction work has increased commensurate with the increased requirements for construction materials for the tailings management facility, rather than to supply material to the process plant. The updated mine plan contemplates a cutoff strategy pursuant to which the mine is operated for the first six years of production at cutoff grades that are higher than the traditional break-even point. This strategy results in the head grades for the first four years of production being in excess of two grams per tonne gold. The mine plan produces a mine operating life of 14 years through the selection, production and processing of higher-grade material in the initial years of operation, while stockpiling lower-grade material. Once active mining operations cease after the 14th year, the 31.9-million-tonne stockpile of lower-grade material will be reclaimed and processed for an additional three years of process plant operation. As the updated mine plan schedules the Cirnic pit to be mined out prior to the Cetate pit, the Cirnic pit will be backfilled in the later years of the mine life. Process plant During basic engineering, a number of modifications were made to the flowsheet and process plant in order to better accommodate the winter climate at Rosia Montana, as well as to enhance the environmental protection aspects of the project. The addition of a cyanide destruct circuit to the process plant design, using the SO2/air process, eliminates the concerns associated with discharging cyanide into the TMF. The addition of a plant to treat acid rock drainage provides additional environmental safeguards. Additional metallurgical testwork, as recommended in the feasibility study of August, 2001, was conducted by SGS-Lakefield Research, of Lakefield, Ont., in order to investigate the suitability of the gravity circuit design. The testwork indicated an improved gold and silver recovery by producing and regrinding a sulphide gravity concentrate. Accordingly, the flowsheet was modified to include in-line pressure jigs and three vertical grinding mills. Overall gold recoveries have improved to 82.3 per cent, with overall silver recoveries improving to 58.1 per cent. Tailings management facility A significant geotechnical program, including 100 drill holes and 70 test pits, was recommended by SNC and undertaken by Gabriel in 2002 in order to support the design of the TMF, as well as to study the plant site, waste dumps and open-pit areas. The results of the geotechnical work indicate that more than twice the volume of material than previously predicted must now be removed in order to provide access to competent bedrock for the foundation of the TMF dam wall. The TMF will generally require one additional lift for each year of active mine operations. The TMF uses a centreline method of construction and was developed in accordance with all internationally and Romanian accepted standards in order to provide a zero-discharge facility for the safe and environmentally stable storage of process tailings. The design for the TMF has been certified by independent Romanian dam experts and specialists and has also been subjected to a third party review by Montgomery Watson Harza, of Denver, an independent international consulting firm specializing in tailings dam design and construction. Capital costs Initial capital costs, as set out in the control estimate included as part of the basic engineering, will be approximately $437-million (U.S.), which amount includes a contingency of approximately $43-million (U.S.). Items of the initial capital cost that have experienced the greatest increase, together with the approximate magnitude of the increase, are set out below. Cost variance figures are in millions of dollars.
Cost Initial capital cost item variance
Mining, increase in mining fleet $26 Process plant, support caissons 2 Process plant, addition of gravity circuit 4 Process plant, lime-handling facilities 1 Process plant, cyanide destruct SO2/air circuit 4 Tailings management facility 53 Acid rock drainage plant 4 Environmental, water management dams and ponds 14 EPCM fees, to reflect higher initial capital costs 12 Community development, acceleration of village relocation 38 Community development, regional socioeconomic development activities 3 Archaeological and cultural heritage program expansion 2 Owners' costs and insurance 17 --- Total 180 Total initial capital costs relating to mining are $53-million (U.S.) and consist primarily of the mining equipment and fleet necessary to conduct mining operations. These costs have increased due to the inclusion of additional haul trucks and shovels to accommodate the accelerated mining rate necessary to optimize the increased head grades reflected in the updated mine plan during the initial five years of production. Total initial TMF costs of $78-million (U.S.), which include $29-million (U.S.) of preproduction mining costs, reflect the increase in both the quantities and the cost of material to be used in the construction of the TMF resulting from the geotechnical investigations conducted during 2002. Process plant and infrastructure costs for the mine complex have increased slightly, to $146-million (U.S.), due to the addition of the SO2/air cyanide destruct circuit at a cost of approximately $4-million (U.S.), the addition of a gravity circuit at a cost of $4-million (U.S.), together with some minor modifications at a cost of $3-million (U.S.). These incremental costs to the process plant are more than compensated for by the environmental benefits provided by the addition of these items to the project. Environmental costs have increased by approximately $18-million (U.S.), represented by $14-million (U.S.) to accommodate necessary water management dams and storm water ponds, to address and manage historical acid rock drainage impacts of the project, and $4-million (U.S.) for the addition of an acid rock drainage plant. An additional $12-million (U.S.) has been added to EPCM costs as a result of the overall increase in initial capital cost, and $17-million (U.S.) has been added to cover corresponding increases in owners' costs and insurance. Due to the continuing success associated with the community development program, Gabriel has brought all sustaining capital costs forward into initial capital costs, thereby increasing initial capital costs by $38-million (U.S.) to $63-million (U.S.). By accelerating the community development program, Gabriel will compress the time frame required to complete all three phases of the program. Phase 1 of the community development program was originally designed to cover all properties required for construction of the project, phase 2 covered all properties located in areas impacted during the initial seven years of the mine life and phase 3 covered the balance of properties in areas affected during the balance of the project's mine life. Overall sustaining capital has witnessed a net reduction of $2-million (U.S.) down to $123-million (U.S.). The savings of approximately $38-million (U.S.) resulting from the acceleration of the community development program are offset by the sustaining capital for the TMF having increased by $24-million (U.S.) to $47-million (U.S.) to reflect the greater quantities of material required for subsequent lifts, together with $10-million (U.S.) in additional environmental and mine closure costs. Operating costs Cash operating costs average $107 (U.S.) per ounce of gold recovered, net of silver credits, over the initial five years of mine life, and average $144 (U.S.) per ounce over the life of the mine. Total cash costs average $115 (U.S.) per ounce of gold recovered, net of silver credits, over the initial five years of mine life, and average $152 (U.S.) per ounce over the life of the mine. Total production costs average $174 (U.S.) per ounce of gold recovered, net of silver credits, over the initial five years of mine life, and average $221 (U.S.) per ounce over the life of the mine. All per-ounce calculations of costs have been made in accordance with the guidelines established by the Gold Institute. Per-tonne on-site operating costs, including costs for mining, processing, cyanide destruction, tailings, and general and administrative costs, average $7.18 (U.S.) over the initial five years of mine life, and average $6.48 (U.S.) over the life of the mine. The two principal components of the increase in cash costs are electric power costs and reagent costs. Power costs are estimated in the control estimate at approximately four cents per kilowatt hour (kWh), as opposed to previous estimates of 2.2 cents per kilowatt hour. Gabriel is currently in discussions with a variety of power suppliers in Romania with a view to ascertaining whether lower prices can be obtained through long-term fixed-price power contracts. Higher reagent costs can largely be attributed to the addition of neutralizing chemicals within the cyanide destruct circuit inside the process plant, together with a modest increase in the consumption of cyanide. Average total cash operating costs for the initial five years of mine life remain in the lowest quartile of cash operating costs in the gold mining industry, and remain at the very lower end of the second quartile for the life of the mine. Executive summary of the basic engineering The executive summary of the basic engineering will be filed on Sedar within 30 days of the issuance of this news release and will be available on the Sedar Web site (www.sedar.com). Community development, resettlement and relocation program After discussions with the World Bank Group and the IFC during mid-2002, Gabriel elected to update, upgrade, and improve the resettlement and relocation plan (the RAP), in order to bring it into more detailed compliance with all relevant World Bank Group/IFC guidelines and policies. The updated RAP was completed and published on Jan. 31, 2003. A copy of the RAP is available on Gabriel's Web site at www.gabrielresources.com, as well as in the community information centre located in Rosia Montana. The RAP will also form an integral part of the environmental and social impact assessment presently being prepared for the project. With the finalization and publication of the updated RAP, Gabriel has recommenced making payments to property owners which have negotiated resettlement or relocation packages and entered into legal purchase agreements. In addition, Gabriel has now ceased making the one-time delay payments, in an amount equal to 3 per cent of the value of a property, which began in August, 2002, pending completion of the updated RAP. At the present time, approximately 20 per cent of all local property owners in Rosia Montana have entered into purchase agreements with Gabriel. Support for the project from the local community and all levels of the Romanian government continues to be strong. Archaeological discharge program Following the approval of the National Archaeological Commission in December, 2002, the Romanian minister of culture has issued an archaeological discharge certificate to Gabriel for the balance of the project's plant site and associated infrastructure, as well as the area in the Corna valley required for the TMF. Gabriel has now completed archaeological investigations and received discharge certificates for all of the principal areas necessary to commence construction of the project. As part of the program conducted during 2002, Gabriel agreed to preserve in situ a circular funerary structure identified during the 2002 program. This structure is not located in the areas required for mining and processing and will not impact the development of the project. During 2003, additional archaeological investigations will be undertaken on the Jig and Orlea areas, which are currently scheduled to enter into production later in the project's mine life. Environmental impact assessment The Romanian government has recently enacted an updated environmental law and associated regulations regarding the preparation of environmental impact assessments, in order to harmonize its environmental laws and regulations with those of the European Union. The new laws will enable Gabriel to apply for and receive an integrated approval for all environmental aspects of the development and operation of the project, as well as to ensure appropriate public participation in the permitting process, consistent with the EU's current practice. The EIA for the project is currently under preparation and is scheduled for submission to the Romanian government during the third quarter of 2003. In October, 2002, the project description was submitted to the Romanian government as the initial step in the EIA process, a copy of which was posted in October, 2002, on the Web site of Rosia Montana Gold Corporation SA, Gabriel's 80-per-cent-owned Romanian subsidiary, at www.rosiamontanagoldcorp.com. Gabriel's corporate policy regarding the environmental aspects of the development of the project is to fully comply with all relevant World Bank Group guidelines and policies, European Union directives, and Romanian laws and regulations. To assist Gabriel in meeting these guidelines and policies, Gabriel has engaged, after extensive discussion and consultation with the IFC during 2002, a number of internationally recognized experts in environmental matters relating to the development of mining projects, to assist in the preparation of the EIA. An integral part of the design of the project is the inclusion of a state-of-the-art cyanide destruct circuit using the SO2/air process, which will reduce the levels of cyanide being placed into the TMF to less than one part per million. Discharge levels of less than one part per million of cyanide are well below current World Bank Group/IFC guidelines and policies, European Union directives, and Romanian laws and regulations for mining projects, and will make the project one of the most environmentally friendly mines in Europe. EPCM contract tender issued Gabriel has issued an international tender for an engineering, procurement and construction management contract to provide all necessary engineering support for the permitting of the project, as well as for the detailed engineering and construction phases of the project. Project financing With the conclusion of the basic engineering, Gabriel is currently reviewing a variety of potential sources of financing for the project with a view to arranging the most appropriate financing package to advance the future development of the project. As part of that review, Gabriel will continue its discussions with a number of commercial banks regarding the provision of project debt financing. Project development plan, 2003 Gabriel's project development plan for 2003 is focused on the key items necessary to advance the future development of the project. These include acceleration of the community development program and completing the EIA process. Gabriel currently anticipates that the EIA process will be completed during late 2003 in order to allow construction to commence during the third quarter of 2004, with initial gold production anticipated in the second half of 2006. |