We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : Precious and Base Metal Investing -- Ignore unavailable to you. Want to Upgrade?


To: E. Charters who wrote (25991)12/28/2003 7:51:25 AM
From: Condor  Read Replies (1) | Respond to of 39344
 
I am debating about drifting and raising.

The raise bore m/c also requires an overcut and that may not fit your critical path schedule whereby the Alimak .........you know.
Consideration of the rail 2 boom long tom vs. any other method should include the time to cycle/advance needs. It's always disappointing when scheduled 8 ft. rounds have to be scaled back to 6 ft. in order to cycle/shift. It's hard to comment without knowing particulars of your mine design plans/needs. EG: Are you drifting to explore or haulage or both( I presume---hence -Alimak)? Drift sizes and lengths etc.?
I recall about 18 yrs ago our drifting costs for about a 9 x 11 ? were about $ 500/ft. I can't recall if that was track or trackless though.
Are you planning going into a rehab mine or starting anew? If new, addits or shafts??