We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : Mining News of Note -- Ignore unavailable to you. Want to Upgrade?


To: LoneClone who wrote (17691)4/14/2008 10:28:01 PM
From: LoneClone  Read Replies (1) | Respond to of 193999
 
Medusa grows another head in Philippines gold operation

mineweb.co.za

Western Australia-based gold miner Medusa Mining is to build another shaft to expand production from its Co-O gold mine in the Philippines.
Author: Ross Louthean
Posted: Thursday , 10 Apr 2008

PERTH -

Medusa Mining Ltd (ASX & AIM: MML) is to sink a new shaft to an initial depth of 420 metres at the Co-O mine on East Mindanao that will help the company lift annual production to 100,000 ounces.

To be named Hill View, the shaft has a timetable to be hauling ore in the first quarter of 2010.

Medusa's managing director Geoff Davis said this expansion will not interfere with the current production of 60,000 oz per annum.

The Co-O mine has a resource of 713,000 oz at a grade of 10.9 grams/tonne. Probable reserves were 256,000 oz @ a grade of 11.1 g/t gold.

He said the current ongoing drill intersections indicate the deposit is still open along strike in both directions which should enhance resource size.

Davis said if the mine's resource increases then further expansion phases may be considered at a later date, including taking Hill View to a depth of 600m.

The new shaft will have a capacity to hoist up to 700 tonnes per day and when combined with the Agsao, Beta, 3@ and 10@ shafts the hoisting capacity of the mine will be about 1,000t/day.

Davis said a decline development was considered by the company but a series of factors - including high tropical rainfall - meant the shaft sink was more practical. Another factor was decline development would have been costlier.

Davis also said that for a shaft the company only needs to expand its current equipment, spare parts inventories and maintenance requirements using the existing workforce.

The company has finalised land purchases for development of a new tailings dam, to be completed by the end of 2009.