We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Politics : Politics of Energy -- Ignore unavailable to you. Want to Upgrade?


To: RetiredNow who wrote (3991)1/7/2009 11:35:08 AM
From: Road Walker  Read Replies (1) | Respond to of 86356
 
re: Progress Energy Florida Contracts for Two New AP1000 Reactors; Will Retire Two Coal-Fired Units

Yeah I've written about this on the thread.

re: Current plans would be for the units to be operational in the 2016 to 2018 time frame.

My electric bill just went up 20% to pay for the plant which won't go online for for 7 to 9 years.

re: The cost of the two new nuclear units is based on a contract price of $7.65 billion, plus forecasted inflation, owner costs and contingencies. The company estimates the total cost for the two generating units to be approximately $14 billion. This estimate includes land price, plant components, financing costs, construction, labor, regulatory fees and reactor fuel for two units. An additional $3 billion is estimated for the necessary transmission equipment and about 200 miles of transmission lines associated with the project.

$17Billion is a lot of money. I still wonder what you could accomplish by spending the same on solar projects.