Midway Gold (MDW-T) March 3rd 2015 is pleased to announce that construction of the Pan Gold Mine (“Pan”) in Nevada is approximately 93% complete and first gold production is expected by the end of March.
Recent Pan Project Milestones:
On February 7, after six days of irrigation, initial breakthrough of fresh water that had been cycled through the pad was realized.
As of the end of February, 3.1 million tons of ore have been placed on the heap leach pad.
2.0 million tons of ore are currently being irrigated with solution flows to the leach pad at approximately 14% of capacity, as the system ramps up to the design of 5,000 gallons per minute.
Bill Zisch, Midway’s President & CEO commented, “While we have encountered some delays, we continue to make good progress and construction of our Pan gold project is now 93% complete. With recent milestones achieved, we expect first gold production at Pan by the end of March. We have contracted Jacobs Field Services to support commissioning of the process facilities and have moved beyond delays associated with the loss of one of our water wells. In addition, we have secured temporary local occupancy permits that allow us to begin operation of the ADR (Adsorption/Desorption Recovery) plant. We expect to begin leaching with cyanide this week and estimate that we will be able to produce gold approximately twenty days following the application of cyanide solution. We are excited to become a new producing company this month. Generation of revenue from Pan will mark the culmination of a great deal of collective efforts over the past several years.”
Resolution of Previously Announced Delays:
The second production well (PW2) that had a mechanical malfunction on January 1, 2015 was abandoned and a replacement well is approximately 87% complete. Prior to initiating irrigation of the heap, both operating ponds were filled to capacity by pumping solely from the first production well (PW1) at a rate that was below the more productive PW2. While both ponds are now filled, the Company did experienced a delay of several days while the pump motor was replaced on PW1. Having begun irrigation, water is no longer likely to be a source of leaching delays as PW1 has more than adequate capacity to provide make-up water for leach operations as planned. In addition to replacing PW2, Midway will begin developing a permitted third well to support construction of a leach pad expansion scheduled for later this year.
Temporary local occupancy permits have been received for the ADR plant and are not expected to contribute to any further delays.
On-Going Construction:
ADR plant instrumentation and equipment installation, and commissioning of the refinery, represent a majority of the remaining plant construction activities.
The 69 kV power line to the Pan mine is 76% complete with line power expected in early May. In the meantime, mobile generators are providing power to the project. Spending for completion of the power line is expected to be within budget.
Ore control assays, currently outsourced to a commercial lab, are expected to be provided on–site with commissioning of the lab in April.
The total capital expenditure at project completion is estimated to be US$84 million and the estimate of project spending as of January 31, 2015 is approximately US$76 million.
Current Operations and Budgeting:
Contract mining, being performed by Ledcor CMI Inc., has ramped up and is currently exceeding planned production levels of 55,000 tons per day. In 2015 to date, tons mined, including tons placed on the pad, have exceeded budget.
Early sampling of ore grades have generally been below modeled grades with tonnage variances being both positive and negative. As is appropriate during start-up of a mine when observing initial variances averaging below expectations, the Company has engaged an independent engineering firm to review modeling, sampling, and assaying practices to gain an informed understanding of tonnage and grade variances to date. Sustained gold production from the heap will provide an additional data point from which to complete an assessment of initial model performance and will provide the first estimate of actual gold recoveries.
During 2015, near mine exploration expenditures at Pan are budgeted at US$2.5 million. Exploration drilling of the South Pan deposit will target expanding the northern and southern extensions of the existing resource along with targeting of the Wendy Deep zone. Step-out drilling in these areas will allow us to evaluate the potential to upgrade resources to reserves and exploration drilling will allow us to evaluate expanding the resources as these areas remain open at this time. While there is no assurance of exploration success, the objective of the exploration program is to determine if the mine life at Pan can be extended or production expanded.
Midway has drawn US$47.5 million of the US$53 million project finance facility held with Commonwealth Bank of Australia (“CBA” or the “Lender”). The Company is required to satisfy certain covenants, tests and obligations related to the facility, including schedule and other contingencies, in order to continue to draw amounts available under the facility and to remain in compliance with its terms. Based on current projections, a two week delay from an internal targeted mid-March pour will likely now result in a working capital shortfall of about US$5 million. In addition, Midway is working through the terms of a credit amendment with the Lender. As a contingency, these terms may require the Company to fund project working capital for a scenario under which first production is assumed to be May 1, 2015 and potentially defer project distributions which could increase corporate working capital needs from prior estimates. The Company’s performance in the coming weeks will impact the amount of these contingencies and Midway is evaluating alternatives to fund working capital needs.
Sustaining capital in 2015 includes US$8 million for construction of the second stage of the heap leach pad at Pan. This expansion, anticipated for completion by September 2015, is planned to more than double leach pad capacity. A total of 2.2 million square feet, capable of holding up to 12 million tons, will be added to the existing pad, which has a current capacity of approximately 8 million tons.
Gold Rock Development Activities:
The team that successfully led Pan through the timely completion of the National Environmental Policy Act (NEPA) permitting process have now shifted their attention to Gold Rock, with activities this year focused primarily on the funding of the NEPA process and the collection of baseline data. On February 13, the Company received its Notice of Availability (NOA) from the Nevada Bureau of Land Management (BLM) for Gold Rock and has initiated a public comment period that will conclude on March 30, 2015. Approximately US$1 million is budgeted for Gold Rock permitting activities in 2015.
About Midway Gold Corp.
Midway Gold Corp. is a precious metals company with a vision to explore, design, build and operate gold mines in a manner accountable to all stakeholders while seeking returns for shareholders.
The scientific and technical information in this release has been reviewed and approved for Midway Gold Corp. by Eric LeLacheur, Nevada District Geologist, and “Qualified Person” as defined under NI 43-101.
Midway Gold Corp. Jaime Wells, 720-979-0900 Investor Relations www.midwaygold.com |