We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : Copper Fox -- Ignore unavailable to you. Want to Upgrade?


To: Metacomet who wrote (9647)9/23/2015 1:33:18 AM
From: louel3 Recommendations

Recommended By
biggerbob68
Hog Head
Theotokos

  Respond to of 10654
 
I think you are generalizing or painting all oil sands projects with one brush. When they say the cost of new projects will be 50 to $90 per Bbl. That is probably true. However the costs vary from one to another. some are extremely high while others on the other end of the price range are quite low. As a group they produce an average cost. The highest cost projects have been delayed, some even foreseeably cancelled.

Ft.Hills is a very high grade deposit and at the extreme low end of the group cost average.

The following is from a research firm;

The Fort Hills oil sands project has been in the works for over a decade, the partners announced that they will commit $13.5 billion to building it with a start-up date set for the end of 2017. The costs as well as the profits – will be shared by the joint venture partners Suncor, Total E&P, and Teck. Suncor is the project builder and operator by virtue of its many decades of experience in the Alberta oil sands.

We first heard of Fort Hills in 2002 when the first phase start-up date of 2005 was announced.

We wrote the first detailed article about Fort Hills in the June 2006, when we spoke at length with Teck about its participation. By that time the cost of building an operation with an output of 100,000 bbl/day had jumped to $5 billion, and a 2010 start-up was expected. Expansion, again to 190,000 bbl/day, was estimated to cost another $5 billion.

For a project that was having trouble getting the full go-ahead, it just kept getting bigger. By 2007 a 140,000 bbl/day phase one would need a $14.1 billion commitment. First production would have been 2011. And the second phase expansion to 280,000 bbl/day carried a $12.1 billion price tag.

Then came the financial meltdown of 2008. The partners announced that they would delay a final decision on Fort Hills. With an estimated 4.4 billion bbl of bitumen in the ground, work slowed until 2011 when Suncor and Total struck an agreement. Production is slated to begin 2017.

Behind the scenes Suncor has poured over the costs and the many lessons to be learned from other oil sands projects. Having completed $20 billion in oil sands projects in the past four years – all of which came in under budget – the company is confident it can bring in the Fort Hills project without cost overruns.

During construction the number of workers in camp on site will be between 5,000 and 5,500. By spreading the work more evenly during the timeline, there will be no ballooning back end costs. There will be some fluctuations in labour demand and the capital spending will rise and fall, but there will be no need to throw indiscriminate amounts of money at Fort Hills to meet the start-up deadline. Suncor added that construction will require 47,000 person years of work, 21,000 of which will be sourced in Alberta.

Suncor's innovative TRO™ technology will be applied to the tailings management facility. This will allow more timely reclamation of the ponds as the mature fine tails can be settled and keeps the project footprint smaller.

The numbers for the Fort Hills project were determined using a conservative price of $50 to $60 per barrel of bitumen. There is much profit to be made even at that price as operating costs are estimated at $20 to $24 per barrel. At the target output of 180,000 bbl/day, 365 days/year the potential is staggering. Now multiply that by at least 50 years of operation using a 3.3 billion bbl resource, and the scope of Fort Hills is gigantic – for Alberta and for Canada.

Even at a pre-production capital cost of $13.5 billion, the price of the Fort Hills project could look like a bargain 50 years from now.

Oil like anything else is subject to price cycles. The long term average is what counts.

Ruchir Sharma at Morgan Stanley Investment Management Inc. That makes a barrel of oil at around $50 just about right based on a 100-year inflation-adjusted average. Sharma manages $25 billion as head of emerging markets