We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : Pacific Rim Mining V.PFG -- Ignore unavailable to you. Want to Upgrade?


To: Ross Mickey who wrote (8368)1/6/1998 12:11:00 PM
From: Quickdraw  Respond to of 14627
 
Hi Ross:

Thanks for sharing that. I note from the prospectus that the following work will be done on the La Colorada property in 1998
... so we should see it come to life early this year.

La Colorada:

In addition, the Issuer must undertake a program of work to be completed by January 25, 1999, consisting of the following:

Description of Work Duration of Work Projected Cost ($US)
detailed geological mapping at a scale of 1:2,000 and 1:1,000 30 days $ 70,000
detailed geophysics using electrical methods 20 days $ 55,000
detailed geochemical surveys 20 days $ 35,000
3,000 meters of diamond and/or reverse circulation drilling 65 days $ 540,000
analysis of results of work to date 20 days $ 47,000
6,000 meters of diamond drilling 90 days $ 780,000
metallurgical studies 30 days $ 220,000
Estimated Totals: 1,600 days US$2,000,000



To: Ross Mickey who wrote (8368)1/6/1998 2:40:00 PM
From: Bill Jackson  Read Replies (1) | Respond to of 14627
 
Ross; That looks good, but the Colorada stuff looks dated?, as they disposed of that stuff last year and staked smaller zones?

Bill