We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Politics : Formerly About Advanced Micro Devices -- Ignore unavailable to you. Want to Upgrade?


To: Brumar89 who wrote (1024165)7/9/2017 5:02:31 PM
From: Brumar89  Read Replies (1) | Respond to of 1578695
 
Re Trump & LNG to Poland: Trump doesn't have any LNG to sell. Cheniere does and their export terminal that opened in 2016 began development in 2010. Trump had nothing to do with it and has nothing to say about the price either. That's negotiated by the parties to the transaction NOT a national commissar. His and his Trumpettes claims that Trump is selling LNG to Poland but wanting more money for it are blather. Exactly like Obama taking credit for the US drilling industry's successes.

.... The U.S. started to export LNG from the lower 48 states when the first liquefaction train at the Sabine Pass terminal in Louisiana, built by Cheniere, opened in February 2016. Five additional export terminals are expected to open by 2020, built by units of Dominion Resources Inc ( D.N), Kinder Morgan Inc ( KMI.N), Sempra Energy ( SRE.N) and Freeport LNG.

Prior to this, the only natural gas exports from the lower 48 states were via pipeline to Mexico, and the U.S. was a net importer overall of natural gas from Canada.

reuters.com



Loading of the first commissioning cargo at the Sabine Pass LNG Terminal - February 2016

http://www.cheniere.com/terminals/sabine-pass/

Sabine Liquefaction Project Schedule Trains 1 – 4July 26, 2010 – Submitted NEPA Pre-Filing Request
August 4, 2010 – Received FERC Approval to use Pre-Filing Process
January 31, 2011 – Filed NGA Section 3 Application
December 28, 2011 – Issuance of Environmental Assessment / Environmental Impact Statement
January 31, 2012 – Filed Initial Implementation Plan
April 16, 2012 – Issuance of Authorization
August 9, 2012 – Commenced Construction
February 24, 2016 – Exported First Commissioning Cargo from Train 1http://www.cheniere.com/terminals/sabine-pass/trains-1-6/project-schedules/