We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Strategies & Market Trends : The Financial Collapse of 2001 Unwinding -- Ignore unavailable to you. Want to Upgrade?


To: elmatador who wrote (4442)2/18/2020 11:48:41 AM
From: kidl2 Recommendations

Recommended By
elmatador
Elroy Jetson

  Read Replies (1) | Respond to of 13801
 
The German permit situation needs some clarification. It was Tesla which chose to commence site work at their own risk even though the public comment / objection period doesn’t end until March 05 with public discussion scheduled for March 18. Until such time no site preparation / building permits have or can be granted.

Strictly speaking, the site preparation work which has taken place to date is unlawful. Tesla and its German lawyers certainly knew this but chose to “gamble”. BTW, German building / construction permit regulations are in line with those of the majority of Western European countries.

Tesla and its fan club made the potential mistake of assuming that European timetables will match those just seen in China.

That said, Germany should and likely will do everything to speed up this project but it can’t and shouldn’t be expected to simply throw out longstanding regulations.