Deep South PEA update returns significantly improved economics 	   
  deepsouthresources.com    	Vancouver, B.C., Canada – December 15, 2020 – Deep-South Resources Inc. ("Deep-South" or “the Company") (TSX-V: DSM). ) today announced that it has received the results of the updated Preliminary Economic Assessment ("PEA") from METS Engineering Group (“METS”) on its Haib Copper Project in Namibia. Further to recent increases in the copper price to well over $3.00 per lb, Deep-South revised the Preliminary Economic Assessment ("PEA") on its 100% controlled Haib Copper Project in Namibia.
   Pierre Leveille, President & CEO of Deep-South stated that: "We  are extremely encouraged by the results of our updated PEA: its  economics have improved dramatically. Our base case model using a price  of US $ 3.00 per lb shows an after-tax NPV of US $957million and an  after tax IRR of 29.7%. Moreover, at a copper price of $3.50 per lb our  Haib Copper project shows an after-tax NPV of US $ 1.3 billion and an  after tax IRR of 42.1%. Of note, our current market capitalization is  only 0.8% of this NPV. We are highly encouraged by the solid copper  market outlook and with the funds in-hand we are confident that our  coming exploration and development program will bring strong added value  in 2021 and onward.” 
   Our base model is as follows:
   The deposit showed to be amenable to bio-heap leaching;Throughput of 20 Mtpa;Copper recovery of 80%;Production of 35,332 tpa copper cathodes and 51,080 tpa copper sulfate;Copper price US $ 3.00 per lb: after-tax NPV US $ 957 million and IRR: 29.7%;Low Capex at US $341 million;Low-strip ratio at 1.41:1;After-tax payback: 4.23 years;Life of mine : 24 years.  
   The updated report will be filed soon on SEDAR under  Deep-South's profile and on the web site of the company. Our  shareholders will be informed timely.
   Highlights of the PEA
   The recent leaching test-work was carried out by Mintek of South Africa. Mintek is a world leader in Bio-leaching technologies.
   Amenability test work confirmed copper recoveries of up to  95% in bacterially assisted heap leaching of the Haib mineral. The  tests were carried out in 1 meter columns and the recoveries in large  leach pads on site can differ from the columns test work. However,  recoveries of 80% and 82% were showed to be very achievable and  sustainable for the project from the test-work to date and were chosen  as base model recoveries.
   Further work is required in order to refine and optimize process conditions to improve recoveries and operating costs.
   Run-of-Mine mineral Bio heap leaching was determined to be  the most viable process route for the Haib mineral. Six processing  scenarios were established with the key variables being recoveries,  final products (copper cathode and copper sulfate) and metal price. The  base case chosen by Deep-South is the scenario (1) below, which is  based on the production of copper cathodes and copper sulfate. All  financial metrics are based on the recent 43-101 indicated resource  estimation of 456.9 MT @ 0.31% Cu:
    Table 1: Scenario 1 - project metrics
      | 20 Mtpa @ 80% Cu Recovery + CuSO4 |      LME Cu, tpa
    |   35,332
    |      CuSO4.5H2O, tpa
    |    51,081 
    |      CAPEX, (US$M)
    |    $341
    |      OPEX, (US$M / year)
    |    $91
    |      Total Cost, US$/t ROM
    |    $7.73
    |      Total Cost, US$/lb CuEq
    |    $1.36
    |      Copper Price, US$/lb
    |   $2.50
    |   $3.00
    |   $3.25
    |   $3.50
    |   $4.00
    |      Avg. Annual Revenue LME Cu (US$ Million/year)
    |   $195 Million
    |   $234 Million
    |   $253 Million
    |   $273 Million
    |   $312 Million
    |      Avg. Annual Revenue CuSO4 (US$ Million/year)
    |   $90 Million
    |   $108 Million
    |   $116 Million
    |   $125 Million
    |   $143 Million
    |      Total Cost, USD/t ROM
    |   $7.64
    |   $7.73
    |   $7.77
    |   $7.81
    |   $7.90
    |      Total Cost, USD/lb CuEq
    |   $1.34
    |   $1.36
    |   $1.37
    |   $1.37
    |   $1.39
    |      NPV 7.5%, pre-tax (US$ M)
    |   $977 Million
    |   $1,530 Million
    |   $1,807 Million
    |   $2,083 Million
    |   $2,636 Million
    |      IRR pre-tax
    |   30.1%
    |   40.2%
    |   44.9%
    |   49.4%
    |   58.1%
    |      Payback Period pre-tax
    |   4.22
    |   3.13
    |   2.8
    |   2.5
    |   2.2
    |      NPV 7.5%, after-tax (US$ M)
    |   $611 Million
    |   $957 Million
    |   $1,130 Million
    |   $1,303 Million
    |   $1,648 Million
    |      IRR after-tax
    |   22.7%
    |   29.7%
    |   32.9%
    |   36.1%
    |   42.1%
    |      Payback Period after-tax
    |   5.71
    |   4.23
    |   3.8
    |   3.4
    |   2.8
    |      Strip Ratio
    |    1.41:1
    |      LOM, years
    |    24
    |       Note: The PEA is based only on the estimated indicated  resource and the inferred resource are not part of this economic  assessment
   With further metallurgical work and testing, the company's  goal is to attain higher recovery rates. The below scenario (2)  illustrate the potential economic upside of higher recoveries:
   Table 2: Scenario 2 - project metrics
        20 Mtpa @ 85% Cu Recovery + CuSO4
    |      LME Cu, tpa
    |    38,337
    |      CuSO4.5H2O, tpa
    |    51,081
    |      CAPEX, (US$M)
    |    $341
    |      OPEX, (US$M / year)
    |    $96
    |      Total Cost, US$/t ROM
    |    $8.00
    |      Total Cost, US$/lb CuEq
    |    $1.33
    |      Copper Price, US$/lb
    |   $2.50
    |   $3.00
    |   $3.25
    |   $3.50
    |   $4.00
    |      Avg. Annual Revenue LME Cu (US$ Million/year)
    |   $211 Million
    |   $254 Million
    |   $275 Million
    |   $296 Million
    |   $338 Million
    |      Avg. Annual Revenue CuSO4 (US$ Million/year)
    |   $90 Million
    |   $108 Million
    |   $116 Million
    |   $125 Million
    |   $143 Million
    |      Total Cost, USD/t ROM
    |   $7.91
    |   $8.00
    |   $8.05
    |   $8.09
    |   $8.18
    |      Total Cost, USD/lb CuEq
    |   $1.32
    |   $1.33
    |   $1.34
    |   $1.35
    |   $1.36
    |      NPV 7.5%, pre-tax (US$ M)
    |   $1,088 Million
    |   $1,673 Million
    |   $1,966 Million
    |   $2,259 Million
    |   $2,844 Million
    |      IRR pre-tax
    |   32.2%
    |   42.6%
    |   47.5%
    |   52.2%
    |   61.1%
    |      Payback Period pre-tax
    |   3.94
    |   2.94
    |   2.6
    |   2.4
    |   2.0
    |      NPV 7.5%, after-tax (US$ M)
    |   $681 Million
    |   $1,047 Million
    |   $1,229 Million
    |   $1,412 Million
    |   $1,778 Million
    |      IRR after-tax
    |   24.1%
    |   31.3%
    |   34.7%
    |   38.0%
    |   44.3%
    |      Payback Period after-tax
    |   5.34
    |   3.98
    |   3.5
    |   3.2
    |   2.7
    |        Strip Ratio
    |    1.41:1
    |        LOM, years
    |    24
    |       Note: The PEA is based only on the estimated indicated  resource and the inferred resource are not part of this economic  assessment
   Please note that: Mineral  Resources that are not mineral reserves do not have demonstrated  economic viability. Mineral resource estimates do not account for  mineability, selectivity, mining loss and dilution. These mineral  resource estimates ar based on Indicated Mineral  Resources that are considered too speculative geologically to have the  economic considerations applied to them that would enable them to be  categorized as mineral reserves. However, there is no certainty  that these indicated mineral resources will be converted to measured  categories through further drilling, or into mineral reserves, once  economic considerations are applied. There is no certainty that the preliminary economic assessment will be realized.
   Other scenarios
   The other scenarios can be found  in the NI 43-101 technical report for the Haib Copper project that is  available on SEDAR under Deep-South's profile and on the web site of the  company.
   Geology & Mineralization
   The Haib deposit is located within part of the  Namaqua-Natal Province called the Richtersveld geological sub-province  which is further subdivided into a volcano-sedimentary sequence  (locally, the Haib Subgroup), the Orange River Group and the intrusive  Vioolsdrift suite which are closely related in space and time.
   The principal mineralized hosts at the Haib are a Quartz Feldspar Porphyry (QFP) and a Feldspar Porphyry (FP).
   The Haib deposit is, in essence, a large volume of rock  containing copper mineralization. The grade is variable from higher  grade in the three core zones progressively dropping towards the margin  of the deposit.
   The principal sulfides within the Haib body are pyrite and  chalcopyrite with minor molybdenite, bornite, digenite, chalcocite and  covellite.
   Mineral Resources
   The mineral resources for the Haib Copper Project were  estimated by Dean Richards of Obsidian Consulting Services, supervidsed  by Peter Walker of P & E Walker Consultancy, both independent  Qualified Persons as defined by NI 43-101 and were reported in a news  release dated January 16, 2018 but are summarized below for convenience.  Readers should review that news release for additional information or  read the full report that can be viewed on our web site at: deepsouthresources.com or on the SEDAR web site at: www.sedar.com.
   Table 3: Classified Mineral Resources of the Haib Project at a 0.25% Cu Cut-Off Grade
       Resource Class
    |   xMillion Tonnes
    |   Cu(%)
    |   Contained Cu x billion lbs
    |      Indicated
    |   456.9
    |   0.31
    |   3.12
    |      Inferred
    |   342.4
    |   0.29
    |   2.19
    |       Notes:
   1- Dean Richards of Obsidian Consulting Services, a  Member of the Geological Society of South Africa and Professional  Natural Scientist (Pr. Sci. Nat) with the South African Council for  Natural Scientific Professions (SACNASP), estimated the Mineral  Resources under the supervision of Peter Walker of P & E Walker  Consultancy, both of whom are the Qualified Persons for the Mineral  Resource Estimates. The effective date of the estimate is January 15,  2018. Mineral Resources are estimated using the CIM Definition Standards  for Mineral Resources and Reserves (2014).
   2- Reported Mineral Resources contain no allowances for  hanging wall or footwall contact boundary loss and dilution. No mining  recovery has been applied.
   Rounding as required by reporting guidelines may result  in apparent differences between tonnes, grade and contained metal  content.
   Table 4: Haib Copper Indicated Mineral Resources, Sensitivity Cases
       %Cu Cut-off
    |   xMillion Tonnes
    |   Cu(%)
    |   Contained Cu x billion lbs
    |      0.20%
    |   904.8
    |   0.27
    |   5.39
    |      0.25%
    |   456.9
    |   0.31
    |   3.12
    |      0.30%
    |   219.8
    |   0.36
    |   1.74
    |       Table 5: Haib Copper Inferred Mineral Resources, Sensitivity Cases
       %Cu Cut-off
    |   xMillion Tonnes
    |   Cu(%)
    |   Contained Cu x billion lbs
    |      0.20%
    |   686.2
    |   0.26
    |   3.93
    |      0.25%
    |   342.4
    |   0.29
    |   2.19
    |      0.30%
    |   109.8
    |   0.34
    |   0.82
    |       Note: The PEA is based only on the estimated indicated  resource and the inferred resource are not part of this economic  assessment
   This Haib Copper Mineral Resource has been defined by  diamond core drilling covering a total surface area of some 2.6 square  kilometres.
   The mineral resource classification is closely related to  data proximity. Topographic elevations within the mineral resource area  vary from 320m to 640m above mean sea level and average 480m above mean  sea level.
   Indicated resources are constrained between the variable  topographic surface and a horizontal level which is 75m above mean sea  level and within which the majority of the drill and assay data are  constrained. Inferred resources are laterally constrained by the last  line of drill holes and extend vertically from the horizontal surfaces  defined by the +75m and -350m above mean sea level (a block of 425m  thickness) within which there is a lesser data set derived from  drilling.
   Mineralization is open near surface and at depth to at  least 800 metres deep. The Mineral Resource estimate is based on the  results from approximately 66,500 metres of drilling in 196 holes. The  most recent drilling data comes from Teck Resources drilling programs  totalling 14,500 metres (2010 & 2014) and from re-assaying a part of  the 164 historical drill cores which are well preserved on site.  Indicated Resources are defined by a drill grid of 150 metres by 150  metres, while Inferred Resources are defined by a drill grid of 300  metres by 150 metres.
   The Haib Copper exploration licence provides significant  potential for resource expansion, since there is known, but poorly  drilled and assayed, mineralisation beyond the drill grid boundaries and  below the main mineralized body (which covers some 2 square kilometres  of surface area), where a few drillholes from 75m above mean sea level  to -350m above mean sea level (i.e. a thickness of 425m) have shown that  mineralisation is present. The deepest drillhole did not pass out of  mineralized material. In addition, there are 5 satellite mineralized  target areas surrounding the main Haib porphyry body which still require  further evaluation.
   Mineral Resources that are not mineral reserves do not  have demonstrated economic viability. Mineral resource estimates do not  account for mineability, selectivity, mining loss and dilution. These  mineral resource estimates ar based on Indicated  Mineral Resources that are considered too speculative geologically to  have the economic considerations applied to them that would enable them  to be categorized as mineral reserves. However, there is  no certainty that these indicated mineral resources will be converted to  measured categories through further drilling, or into mineral reserves,  once economic considerations are applied. There is no certainty that the preliminary economic assessment will be realized.
   Mineralogy
   The Haib Copper Deposit is a large sulfide mineral  deposit. Copper is mainly present as a sulfide in the form of  chalcopyrite. Copper is also present as oxides (chrysocolla, plancheite,  malachite and azurite), occurring as intrusions in shear zones. Initial  testwork results showed that the Haib mineralisation is a competent  quartz feldspar porphyry rock.
   It can be seen that the main mineral is copper with only  an accessory amount of molybdenum present. The chalcopyrite also occurs  as occasional coarse irregular grains from 0.1 mm to 0.35 mm.
   Mining Methods
   Considering the Haib copper deposit characteristics, the  suitable mine design is based on an open pit method. As the deposit is  basically composed of hard rock material, the mining operations will  involve drill and blast of all excavated material, which will be  segregated by cut-off grade.
   The mining fleet considered for the Haib project would  consist of appropriately sized hydraulic excavators and off highway dump  trucks, depending, supported by standard open-cut drilling and  auxiliary equipment.
   Initial open pit mine design work undertaken indicates a  strip ratio of 1.41:1 for 20 Mtpa. The low strip ratio has a significant  effect on the low operating cost indication of the project.
   Recovery Method
   For the recovery of copper from the Haib deposit, heap  leaching was considered for all options. The primary reasons for the  selection of heap leaching are the low-grade nature of the deposit and  the vast scale of the mineral body. Previous work conducted on the Haib  Project suggested that a conventional crush-grind-float and sale of  copper concentrate is not economically feasible under the current copper  market conditions. The low costs associated with heap leaching compared  to a whole mineral flotation circuit is believed to improve the  viability of the project. Heap leaching is traditionally performed on  oxide material, although there has been increasing development in the  application to acid-insoluble sulfides.
   Previous sighter amenability test-work, carried out by  Mintek, METS and SGS South Africa, suggests that high amounts of copper  can be extracted from the Haib material, up to 95.2% via a bacterial  assisted leaching. However, additional test-work is required to  determine the optimal operating parameters. The system design proposed  will use 3 stage crushing and a mineral sorting system (either on the  primary crushed product or the secondary crushed product depending on  the technology selected) that will provide higher grade mineral to the  heaps. The primary crusher will reduce the rock to 127 mm (gyratory crusher), the secondary crusher to 32 mm (cone crusher) and the tertiary crusher to 5 mm (HPGR). 
     Haib Copper Flow Sheet diagram 
   (on the following page)
    
     Capital Costs
   Table 6: Capital cost breakdown @ 80% Cu recovery at a price of US $ 3.00 per lb of copper
       Direct Cost (US$M)
    |      20 Mtpa
    |      Crushing & HPGR
    |   101.1
    |      Agglomeration & Heap Leaching
    |    43.2
    |      Copper Solvent Extraction
    |    72.9
    |      Iron Removal
    |    6.3
    |      Process and Raw Water
    |    4.1
    |      Reagents
    |    5.0
    |      Services
    |    2.9
    |      Supporting Infrastructure
    |    3.0
    |      First Fill
    |    8.3
    |      Indirect Cost (US$M)
    |  
  |      Working Capital
    |   24.7
    |      Insurance
    |   7.4
    |      EPCM
    |   24.7
    |      Contingency
    |   24.7
    |      Commissioning
    |   5.0
    |      Accommodation & Temp Services
    |   5.0
    |      Spares & Tools
    |   3.0
    |      Total (US$M)
    |   341.3
    |     
  |  
  |       Operating Costs
   Total operating costs, including capital leases as an  operating expense, are estimated in the PEA and are broken down as  follows:
   Table 7: Total Operating Cost Breakdown – Scenario 1
       20 Mtpa @ 80% Cu Recovery + CuSO4 
    |      Area
    |   Annual Cost
    |   Unit Cost
    |   Unit Cost
    |     
  |   (‘000 USD)
    |   (USD/t ROM)
    |   (USD/lb CuEq)
    |      Mining
    |   45,200
    |   2.26
    |   0.40
    |       Processing
    |   90,799
    |   4.54
    |   0.80
    |      Product Freight
    |   3,889
    |   0.19
    |   0.03
    |      Wharfage & Shiploading
    |   432
    |   0.022
    |   0.004
    |      Administration
    |   4,000
    |   $0.20
    |   0.04
    |      Royalty
    |   $2.00
    |   6,824
    |   0.34
    |   0.06
    |     
  |   $2.25
    |   7,677
    |   0.38
    |   0.07
    |     
  |   $2.50
    |   8,530
    |   0.43
    |   0.08
    |     
  |   $2.85
    |   9,724
    |   0.49
    |   0.09
    |     
  |   $3.00
    |   10,236
    |   0.51
    |   0.09
    |      Total
    |   $2.00
    |   151,144
    |   7.56
    |   1.33
    |     
  |   $2.25
    |   151,997
    |   7.60
    |   1.34
    |     
  |   $2.50
    |   152,850
    |   7.64
    |   1.34
    |     
  |   $2.85
    |   154,044
    |   7.70
    |   1.35
    |     
  |   $3.00
    |   154,556
    |   7.73
    |   1.36
    |     
  |  
  |  
  |  
  |  
  |       Note: Mineral Resources that  are not mineral reserves do not have demonstrated economic viability.  Mineral resource estimates do not account for mineability, selectivity,  mining loss and dilution. These mineral resource estimates are based on Indicated  Mineral Resources that are considered too speculative geologically to  have the economic considerations applied to them that would enable them  to be categorized as mineral reserves. However, there is  no certainty that these indicated mineral resources will be converted to  measured categories through further drilling, or into mineral reserves,  once economic considerations are applied. There is no certainty that the preliminary economic assessment will be realized.
   Tailing Disposal
   There will be no tailings. The spent heaps will be  rehabilitated and left in place. Due to environmental reasons and water  resources, the tailings from the pH adjustment process and the iron  removal process will be disposed onto the spent heaps via the method of  filtered dry stacked tailings.
   Environmental considerations
   In terms of environmental aspects, dry stack facilities  offer a number of advantages to other surface tailings storage options –  some of these include:
   Reduced water requirements, principally achieved by  recycling process water and near elimination of water losses through  seepage and/or evaporation; Groundwater contamination through seepage is virtually eliminated; Significant safety improvement with the risk of catastrophic dam failure and tailings runout being eliminated; Easier to close and rehabilitate. Waste rock storage
   It is suggested to consider stockpiling the low-grade  mineral to process it at the end of mine life, in case the copper price  increase considerably by the end of the mine life and/or a new mineral  processing technology be created or developed.
   Products
   LME Copper (cathodes)
   Copper is one of the most widely used metals on the  planet. China, Europe and the USA are the main global consumers of  copper. Copper will be produced on the cathode of the electrowinning  cell as pure sheets, which will be a pure (99%) solid. Pure copper metal  is used for a variety of purposes. The major use is electrical wiring  due to the great electrical conductivity of copper. Additionally, copper  is used in many metal alloys such as brass and bronze, which are  stronger and more corrosion resistant than pure copper.
   Copper Sulfate
   Copper sulfate will be sold as a blue powder when the  crystals are crushed and dried. Copper sulfate is used in multiple  industries such as arts, mining, chemical, pharmaceutical, healthcare  and agriculture. The biggest use is for farming as an herbicide or  fungicide. Additionally, it inhibits the growth of E-Coli. In the  healthcare sector, it is used in sterilizers and disinfectants and can  be used to control proliferation of bacteria and viruses. Industrial  usage could be in adhesives, building, chemical, textile industries,  etc. where it is used to manufacture products like insecticides, wood  preservatives and paints. High purity copper sulfate has a 25% premium  price based on the copper content in the sulfate.
   Sulphur Burning Plant
   The design for each option as it stands involves the  burning of sulphur to produce sulphuric acid. There are several  possibilities for sulphuric acid sourcing, including purchasing from  smelters within Namibia.
   Buying in sulphuric acid at the start of the project life  and building a sulphur burning plant once the project is cash flow  positive may provide a better economic scenario.
   This will allow for the sulphur burning plant capital to be deferred and the payback period to be shortened.
   Recommendations
   The results from the PEA have been promising and provides a  fundamental support for Deep South Resources intention to move the  project towards the Feasibility Study phase on the of the deposit.
   Deep South Resources has set a target of achieving 85%  copper recovery as a basis of design in the feasibility study. Some of  the parameters to be evaluated in the study are:
     Recycled column leachingHigher temperature leachingOptimization of particle sizing for leachingDifferent bacterial strainsResting after 200 days for 30 days and then irrigation for another 30 daysOptimization of leach pH leachOptimization of nutrient addition to the leach    
   Infill drilling in the high-grade area of the deposit,  which can be included in the early part of the mine schedule is  recommended. This will improve project economics in the financial model.
   A drill program of 12,000 meters is recommended to  infill a high grade section of the deposit. With a closer grid spacing, a  high-grade part of the deposit could be included in the first years of  mining to improve the economics and pay-back period.
   Further to the Feasibility Study and the drilling of the  mineral body as above, a small Pilot Plant is recommended on-site to  validate and optimize the process under local conditions. The detailed  engineering information and optimization would provide improved  confidence in proceeding with a commercial operation.
   The work conducted to date provides confidence to move  forward, and there is every possibility of improving copper recovery and  reducing the operating costs further.
   The PEA technical report will be filed on SEDAR at www.sedar.com and on the Deep-South website at www.deepsouthresources.com shortly after the issuance of this news release.
   Project Risks
   Further information about the PEA and the resource  estimate referenced in this news release, including information in  respect of data verification, key assumptions, parameters, risks and  other factors, can be found in the NI 43-101 technical report for the  Haib Copper project that will be filed on SEDAR under Deep-South's  profile.
   Opportunities
   Metallurgical advanced test work;Infill drilling of the high-grade area in order to estimate a measured resource;X-Ray ore sorting test work to define the potential economic enhancementSolar Energy: Given the semi-arid climate of  Namibia, a solar energy farm may be an option for reducing the unit cost  of power. This will also have positive social impacts for the project,  which is expected to have a long life.   Other opportunities are presented in the the NI 43-101 technical report for the Haib Copper project that will be filed on SEDAR under Deep-South's profile.
   Project Expansion: 
   The resource tonnage allows for possible multiple  expansion stages to be executed should the project proceed to once in  production. A staged approach is recommended in order to de-risk the  project by projecting that the project achieves positive cash flow prior  to plant expansions.
   Way Forward
   The results from the updated PEA have been promising,  Deep-South Resources intends to undertake a Feasibility Study for the  deposit as the next phase of the project. The program will include but  not limited to: drilling of the high-grade area in order to define the  grade and estimate a measured resource, detailed mine design, measured  resource definition, metallurgical and process technologies test work,  engineering design and an environmental impact study.
   Quality Control and Assurance and Data Verification
   The independent qualified persons for the Haib Copper PEA are Mr. Damian Connelly of Mineral Engineering and Technical Services, Mr. Peter Walker of  P & E Walker Consultancy and Mr. Dean Richards of Obsidian Consulting Services.
   Obsidian Consulting Services conducted a review of the  QA/QC programme implemented by Teck using the certificates of analysis  received from Acme Labs and provided by Teck.  This  review compared the results of field duplicates, blanks as well as the  various standards utilised with respect to Cu and Mo.
   The design of Teck's drilling programme, quality  assurance / quality control programme and the interpretation of results  were under the control of Teck's geological staff. The QA/QC programme  is consistent with industry best practices. Drill core is logged and cut  onsite, with half-core samples prepared at Analytical Laboratory  Services, Windhoek, Namibia.  Prepared samples are shipped to Acme  Analytical Laboratories, Vancouver, Canada for appropriate base metal  assaying and gold fire assaying techniques.  All analytical batches  contain appropriate blind standards, duplicates and blanks inserted at  regular intervals to independently assess analytical accuracy and  precision.
   Mr. Walker and Mr. Richards reviewed the sample  chain-of-custody, quality-assurance and quality-control (QA/QC)  procedures, and the accreditations of analytical laboratories used by  Teck. The QPs are of the opinion that the procedures and QA/QC are  acceptable to support Mineral Resource estimation. 
   Mr. Walker also audited the assay database, core  logging and geological interpretations and found no material issues with  the data as a result of these audits.
   In the opinion of the QPs, the data verification  programs undertaken on the geological and assay data collected from the  Haib Copper support the geological interpretations and the analytical  and database quality, and the data collected, can support Mineral  Resource estimation.
   Qualified Persons
   Damian E.G. Connelly, BSc (Applied Science), FAusIMM, CP  (Met), Principal Consulting Engineer of METS Engineering Group is the  main author of the Preliinary Economic Assessment report and is  responsible for the technical part of this press release and is the  designated Qualified Person under the terms of National Instrument  43-101.
   Peter Walker B.Sc. (Hons.) MBA Pr.Sci.Nat. of P & E  Walker Consultancy is the main author of the 43-101 resource estimation  report, and is a Qualified Person under the terms of National Instrument  43-101.
   Mr. Dean Richards Pr.Sci.Nat. , MGSSA – BSc. (Hons.) Geology, of  Obsidian Consulting Services is the contributing author of the 43-101  resource estimation report and is a Qualified Person under the Terms of  the National Instrument 43-101.
   About METS Engineering
   Established in 1988 by Damian Connelly, Mineral  Engineering Technical Services (METS) has a reputation for providing  quality service to the global mining industryBased in Perth Australia.  They have served clients all around the world from large companies such  as Rio Tinto to exploration and development companies such as Deep-South  Resources. They provide a comprehensive range of services including:  Mineral processing, Engineering design and hydro metallurgy testwork.
   About Deep-South Resources Inc.
   Deep-South Resources Inc. is a mineral exploration company  largely held by Namibian shareholders and Management - Directors with  24% and Teck Resources Ltd with 23% of Deep-South share capital.
   Deep-South currently holds 100% of the Haib Copper project  in Namibia, one of the largest copper porphyry deposits in Africa.  Deep-South also holds an investment of 75% in the Kapili Tepe Copper  exploration project in Turkey.
   Deep-South’s growth strategy is to focus on the  exploration and development of quality assets, in significant  mineralized zones, close to infrastructure, in stable countries.
   This press release contains certain "forward-looking  statements," as identified in Deep- South’s periodic filings with  Canadian Securities Regulators that involve a number of risks and  uncertainties. 
   There can be no assurance that such statements will  prove to be accurate and actual results and future events could differ  materially from those anticipated in such statements. 
   Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
   More information is available by contacting Pierre Léveillé, President & CEO at
   +1-819-340-0140 or at: info@deepsouthresources.com or  Paradox Public Relations at +1-514-341-0408.
   Cautionary statement on forward-looking information 
   Mineral Resources that are not mineral reserves do not  have demonstrated economic viability. Mineral resource estimates do not  account for mineability, selectivity, mining loss and dilution. These  mineral resource estimates are based on Indicated  Mineral Resources that are considered too speculative geologically to  have the economic considerations applied to them that would enable them  to be categorized as mineral reserves. However, there is no  certainty that these indicated mineral resources will be converted to  measured categories through further drilling, or into mineral reserves,  once economic considerations are applied. There is no certainty that the preliminary economic assessment will be realized.
   Certain statements in this release constitute  “forward-looking statements” or “forward-looking information” within the  meaning of applicable securities laws.
   Such statements involve known and unknown risks,  uncertainties and other factors which may cause the actual results,  performance or achievements of the company, or industry results, to be  materially different from any future results, performance or  achievements expressed or implied by such forward-looking statements or  information. Such statements can be identified by the use of words such  as “may”, “would”, “could”, “will”, “intend”, “expect”, “believe”,  “plan”, “anticipate”, “estimate”, “scheduled”, “forecast”, “predict” and  other similar terminology, or state that certain actions, events or  results “may”, “could”, “would”, “might” or “will” be taken, occur or be  achieved. These statements reflect the company’s current expectations  regarding future events, performance and results and speak only as of  the date of this release.
   As well, all of the results of the 2018 Haib Copper  preliminary economic assessment constitute forward-looking information,  including estimates of internal rates of return, net present value,  future production, estimates of cash cost, assumed long term price for  copper of US$3.00 per pound, proposed mining plans and methods, mine  life estimates, cash flow forecasts, metal recoveries, and estimates of  capital and operating costs. Furthermore, with respect to this specific  forward-looking information concerning the development of the Haib  Copper Project, Deep-South Resources has based its assumptions and  analysis on certain factors that are inherently uncertain. Uncertainties  include among others: (i) the adequacy of infrastructure); (ii)  unforeseen changes in geological characteristics; (iii) changes in the  metallurgical characteristics of the mineralization; (iv) the ability to  develop adequate processing capacity; (v) the price of copper; (vi) the  availability of equipment and facilities necessary to complete  development; (vii) the size of future processing plants and future  mining rates, (viii) the cost of consumables and mining and processing  equipment; (ix) unforeseen technological and engineering problems; (x)  accidents or acts of sabotage or terrorism; (xi) currency fluctuations;  (xii) changes in laws or regulations; (xiii) the availability and  productivity of skilled labour; (xiv) the regulation of the mining  industry by various governmental agencies; (xv) political factors,  including political stability.
   All such forward-looking information and statements are  based on certain assumptions and analyses made by Deep-South’s  management in light of their experience and perception of historical  trends, current conditions and expected future developments, as well as  other factors management believe are appropriate in the circumstances.  These statements, however, are subject to a variety of risks and  uncertainties and other factors that could cause actual events or  results to differ materially from those projected in the forward-looking  information or statements including, but not limited to, unexpected  changes in laws, rules or regulations, or their enforcement by  applicable authorities; the failure of parties to contracts to perform  as agreed; social or labour unrest; changes in commodity prices,  including the price of copper; unexpected failure or inadequacy of  infrastructure, or delays in the development of infrastructure, the  failure of exploration programs or other studies to deliver anticipated  results or results that would justify and support continued studies,  development or operations, and the results of economic studies and  evaluations. Other important factors that could cause actual results to  differ from these forward-looking statements also include those  described under the heading “Risk Factors” in the company’s most  recently filed MD&A filed by Deep-South. Readers are cautioned not  to place undue reliance on forward-looking information or statements.  The factors and assumptions used to develop the forward-looking  information and statements, and the risks that could cause the actual  results to differ materially are set forth in the “Risk Factors” section  and elsewhere in the company’s most recent Management’s Discussion and  Analysis report and Annual Information Form, available at www.sedar.com.
   This news release also contains references to estimates  of Mineral Resources. The estimation of Mineral Resources is inherently  uncertain and involves subjective judgments about many relevant factors.  Mineral Resources that are not Mineral Reserves do not have  demonstrated economic viability. The accuracy of any such estimates is a  function of the quantity and quality of available data, and of the  assumptions made and judgments used in engineering and geological  interpretation, which may prove to be unreliable and depend, to a  certain extent, upon the analysis of drilling results and statistical  inferences that may ultimately prove to be inaccurate. Mineral Resource  estimates may have to be re-estimated based on, among other things: (i)  fluctuations in copper prices or other mineral prices; (ii) results of  drilling; (iii) results of metallurgical testing and other studies; (iv)  changes to proposed mining operations, including dilution; (v) the  evaluation of mine plans subsequent to the date of any estimates; and  (vi) the possible failure to receive required permits, approvals and  licences, or changes to any such permits, approvals or licence. Although  the forward-looking statements contained in this news release are based  upon what management of the company believes are reasonable  assumptions, the company cannot assure investors that actual results  will be consistent with these forward-looking statements. These  forward-looking statements are made as of the date of this news release  and are expressly qualified in their entirety by this cautionary  statement.
   Subject to applicable securities laws, the company does  not assume any obligation to update or revise the forward-looking  statements contained herein to reflect events or circumstances occurring  after the date of this news release.
     
   	  		 			 			News Releases		 	   
     	2020-12-02    Deep-South commissions update of the Haib Copper PEA to reflect higher copper prices  
       	2020-11-23    Deep-South to Drill the Haib Copper project in the south of Namibia  
       	2020-10-26    Deep-South appoints Chad Williams as Director and proceeds with changes to its Board and Management  
       	2020-10-19    Deep-South has raised $2,413,200 after closing a second tranche for $1,040,000 of its private placement  
       	2020-09-30    Deep-South private placement over-subscribed and increases the offering to $2.5 million  
       	2020-09-18    Deep-South closed a first tranche for $1,373,200 of its private placement  
       	2020-09-10    Deep-South private placement over-subscribed and increases the offering to $2 million  
       	2020-09-04    Deep-South will close $1 million on revised terms of its non-brokered private placement  
       	2020-08-17    Deep-South receives Stock Exchange Approval and amends the agreement announced on June 30, 2020  
       	2020-08-05    Deep-South Resources announces a non-brokered private placement  
    	
  	   	 |