SI
SI
discoversearch

We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : Royal Oak-RYO -- Ignore unavailable to you. Want to Upgrade?


To: JERRY GACH who wrote (672)2/16/1998 11:22:00 PM
From: roger fontaine  Read Replies (1) | Respond to of 1706
 
Another small surprise for RYO shareholders which isn't very positive.I have decided to put RYO as a hold for the present.I was going to accumulate soon but because of several uncertainties I am not going to accumulate any more shares for now.

Royal Oak faces possible delay in mine startup

Applies to divert water from B.C. lake

Monday, February 16, 1998
By Allan Robinson
Mining Reporter

Royal Oak Mines Inc. is facing a possible delay in the proposed
April startup of its $427-million Kemess gold and copper mine in
north-central British Columbia because of a shortage of water.

In mid-December Royal Oak applied to the B.C. Ministry of
Environment, Lands and Parks for approval to drain two million cubic
metres of water from Duncan Lake during February and March, but
approval has not yet been granted.

The water project would require construction of a 3.7-kilometre
access corridor for a pipeline and electric power supply system to
allow water pumping.

"It's only a precautionary measure we are taking," Graham Eacott, a
spokesman for Royal Oak, said yesterday. "At this stage it's possible
that we won't need the project."

Mr. Eacott said Royal Oak's preliminary figures suggest the pipeline
would cost $750,000 and it would mean a possible delay in the
startup of Kemess of only two weeks. He added that Royal Oak,
which is based in Kirkland, Wash., is waiting for the construction
permit and expects to make a final assessment on the water diversion
project within two weeks.

In the application for the permit, Larry Connell, the manager of
environmental services for the Kemess project, said the company's
consultants estimate that -- based on average levels of precipitation --
the amount of water required by the mill will exceed the amount of
water projected to accumulate in the mine's tailings pond by 3.6 million
cubic metres. That estimate covers water needs from April, 1998 to
March, 1999.

"Realistically, precipitation runoff would not be available to make up
this shortfall until mid-May and June of 1998," Royal Oak told the
government. That would necessitate a delay in the startup of the mine,
planned for "on or before April 1," and is not a preferred option,
Royal Oak said.

"I can't comment on that [report]," Mr. Eacott said when asked about
Royal Oak's filing to the government.

Royal Oak estimates that the drainage project could reduce the water
level of Duncan Lake by at most 0.8 metres, and would have no effect
on fisheries and wildlife.

Environment ministry officials, however, say the scheme potentially
could affect another lake and stream system into which the water
would be diverted for use by Royal Oak.

The ministry has completed a technical review and recently passed on
the proposal for review by the Tsay Keh Dene Band, which has
retained consultants to study the impact of the proposed lake drainage
on their environment, Peter Freeman, the lawyer for the band, said.

Last June, Royal Oak obtained an injunction permitting the company
to remove a roadblock set up by the band to stop haulage to the mine
construction site. The Indian community lives on the western shore of
Lake Williston, about 350 kilometres north of Prince George.

Royal Oak's original plan had assumed that enough natural water
runoff would have been collected in the tailings pond to allow the mine
to start up in April, said ministry official Egon Weger.

Royal Oak attributed the water shortage to delays in completing the
construction of its dam for the tailings pond in the fall of 1996 because
of a change in location and design.

In its application to the government, filed on Dec. 17, Royal Oak said
it intended to start constructing the pipeline in late December, and
begin pumping on Feb. 1.

The water would be siphoned from Duncan Lake to Kemess Lake
and then to the company's tailings pond. Mr. Eacott said the water
drained from Duncan would be replenished by the spring runoff.

The amount of water being drained from Duncan Lake exceeds the
total volume of water in Kemess Lake.

Royal Oak said in its filing that it needs the additional water before it
can begin milling operations in April, in order to "sustain milling
operations through to the spring freshet [a rush of spring water caused
by melted snow] in June of 1999."

Royal Oak's consultants, Knight Piesold, said in December that based
on its studies, and using "optimistic projections," the amount of water
now available at Kemess mine is about three million cubic metres less
than the amount needed to sustain operations for the first full year.