We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : Mining News of Note -- Ignore unavailable to you. Want to Upgrade?


To: LoneClone who wrote (172588)6/27/2023 3:08:59 PM
From: LoneClone  Read Replies (1) | Respond to of 192531
 
FPX Nickel Confirms Optimization of Baptiste Process Flowsheet, Improving Recovery by 4% for Upcoming Preliminary Feasibility Study

newswire.ca

FPX Nickel Corp. 27 Jun, 2023, 07:00 ET

VANCOUVER, BC, June 27, 2023 /CNW/ - FPX Nickel Corp. (TSXV: FPX) (OTCQB: FPOCF) ("FPX" or the "Company") is pleased to announce completion of the preliminary feasibility study ("PFS") metallurgical testwork campaign with key results supporting the updated concentrator flowsheet and providing a materially improved understanding of the process characteristics of the Baptiste Nickel Project ("Baptiste" or the "Project"). The robust testwork campaign involved multiple bench- and pilot-scale programs, with the resultantly improved process design basis increasing the Davis tube recoverable ("DTR") nickel recovery by 4% in comparison to the recovery assumed in the 2020 preliminary economic assessment ("PEA").










Figure 1 – Optimized Baptiste Concentrator Flowsheet (CNW Group/FPX Nickel Corp.)



Highlights


  • PFS testwork program is complete and results will be fully incorporated into the PFS expected in September 2023
  • The updated concentrator flowsheet increases DTR nickel recovery by approximately 4% to 88.7%, in comparison to the 84.7% DTR nickel recovery assumed in the 2020 PEA
  • DTR nickel is further validated as a geometallurgical screening tool which heightens confidence in the PFS projected metallurgical recovery and resultant metal production profile


  • "Our completed metallurgical testwork campaign has further optimized the process flowsheet and improved the recovery basis for the Baptiste PFS, which remains on schedule for delivery in September 2023," commented Andrew Osterloh, FPX Nickel's Senior Vice-President, Projects & Operations. "The scale and depth of our testwork is more analogous with feasibility study-level testwork and reflects FPX's commitment to the development of this new, yet simple and robust, metallurgical process. These results further validate awaruite's processing advantages to produce a unique, high-grade product with unparalleled flexibility to feed into the stainless steel or battery material supply chains."

    FPX has recently completed the PFS metallurgical testwork campaign, with objectives and key results from each campaign phase presented in Table 1. The overall objectives of the program were to validate and improve the PEA process design basis, provide a robust dataset to support process and engineering optimization for the PFS, and to confirm the consistent metallurgical response of the very large Baptiste deposit. For further information on each of the testwork phases, see the referenced FPX news releases in Table 1.

    Table 1 – PFS Metallurgical Testwork Program Summary



    Phase

    Objective

    Key Results

    FPX News
    Release Date


    1

    Pilot-scale testwork to confirm PEA
    magnetic separation basis using life-
    of-mine composite.

    Magnetic separation configuration
    validated, and results indicated potential
    benefit to preferential grinding.

    Sufficient feedstock generated for Phase 2
    flotation program.

    December 8,
    2021

    Bench- and pilot-scale grindability
    testwork to expand comminution and
    grinding parameter databases.

    PFS-level comminution database
    generated to support engineering
    optimization studies.

    2

    Bench-scale testwork to confirm
    nickel mineralogy across Baptiste
    resource.

    Confirmed consistency of resource
    mineralization and validated DTR nickel
    as a geometallurgical screening tool.

    July 27, 2022

    Bench-scale testwork to confirm
    the PEA conclusion that froth flotation
    can generate high grade nickel
    concentrate.

    Flotation configuration and results
    validated, through the generation of a
    high-grade nickel concentrate (> 60%
    nickel) with strong locked cycle recovery.

    3a

    Large-scale pilot testing to further
    demonstrate the recovery benefits
    observed in Phase 1, and to generate
    sufficient feedstock for Phase 3c
    testwork.

    Further validation of flowsheet,
    confirmation of preferential grinding
    benefit, confirmation of magnetic
    separation intensity benefit, and generation
    of sufficient feedstock for Phase 3c.

    January 24,
    2023

    3b

    Variability testing to confirm the
    homogeneity of the Baptiste resource
    and further validate DTR nickel as a
    geometallurgical screening tool.

    Consistent magnetic separation recoveries
    achieved across all phases of the Baptiste
    mine plan, validating resource
    homogeneity and DTR nickel as a
    geometallurgical screening tool.

    May 3, 2023

    3c

    Hydrometallurgical testing to
    optimize previous leach testing, and
    conduct purification and nickel
    sulphate crystallization testwork.

    Optimization of leaching resulting in
    reduced reagent consumptions and
    simplification of downstream purification
    requirements.

    Production of battery-grade nickel sulphate
    and cobalt precipitate products.

    May 17, 2023




    While the overall PEA processing strategy has remained consistent and takes advantage of awaruite's unique characteristics, unit operations in the concentrator flowsheet have now been refined and are presented in Figure 1.

    Based on the optimized flowsheet and the subsequent PFS design, the estimated life of mine recovery for the PFS is summarized in Table 2. The table also highlights key circuit design changes relative to the PEA, as follows:

  • The PFS design has split cleaning magnetic separation into two stages, cleaning and recleaning, as an engineering optimization to maximum grinding energy efficiency with no significant impact on nickel recovery
  • A flotation tails treatment section, combining the leaching of flotation tailings and the recovery of dissolved nickel, has also been added to the PFS design; this leaching stage accounts for approximately 6.5 percent of the overall DTR nickel recovery



  • Table 2 – Life of Mine DTR Nickel Recovery – PEA vs. PFS



    Recovery

    DTR Nickel Recovery (%)

    PEA

    PFS

    By
    Processing
    Stage

    Roughing Magnetic Separation

    90.1

    95.0

    Cleaning Magnetic Separation

    100.0

    99.3

    Recleaning Magnetic Separation

    99.7

    Flotation

    94.0

    87.4

    Flotation Tailings Treatment

    N/A

    54.8

    Overall

    To Awaruite Concentrate

    84.7

    82.2

    To Mixed Hydroxide Precipitate

    N/A

    6.5

    Combined To Both Nickel Products

    84.7

    88.7




    As seen in Table 2, based on a PFS average feed grade of 0.13% DTR nickel, the optimized PFS flowsheet predicts an 88.7% DTR nickel recovery for the life-of-mine, representing an increase of 4% from the PEA. On a total nickel basis, and based on PFS mineral resource average grade of 0.21% total nickel, the optimized PFS flowsheet achieves 54.9% total nickel recovery.

    Qualified Person
    Jeff Austin, P.Eng., President of International Metallurgical and Environmental Inc. and FPX's Qualified Person under NI 43-101, has reviewed and approved the technical content of this news release.

    About the Decar Nickel District
    The Company's Decar Nickel District represents a large-scale greenfield discovery of nickel mineralization in the form of a naturally occurring nickel-iron alloy called awaruite (Ni3Fe) hosted in an ultramafic/ophiolite complex. FPX's mineral claims cover an area of 245 km2 west of the Middle River and north of Trembleur Lake, in central British Columbia. Awaruite mineralization has been identified in several target areas within the ophiolite complex including the Baptiste Deposit and the Van Target, as confirmed by drilling, petrographic examination, electron probe analyses and outcrop sampling. Since 2010, approximately US $28 million has been spent on the exploration and development of Decar.

    Of the four targets in the Decar Nickel District, the Baptiste Deposit has been the focus of increasing resource definition (a total of 99 holes and 33,700 m of drilling completed), as well as environmental and engineering studies to evaluate its potential as a bulk-tonnage open pit mining project. The Baptiste Deposit is located within the Baptiste Creek watershed, on the traditional and unceded territory of Tl'azt'en Nation and Binche Whut'en First Nation, and within several Tl'azt'enne and Binche Whut'enne keyohs. FPX has conducted mineral exploration activities to date subject to the conditions of our agreements with the Nations and keyoh holders.

    About FPX Nickel Corp.
    FPX Nickel Corp. is focused on the exploration and development of the Decar Nickel District, located in central British Columbia, and other occurrences of the same unique style of naturally occurring nickel-iron alloy mineralization known as awaruite. For more information, please view the Company's website at www.fpxnickel.com or contact Martin Turenne, President and CEO, at (604) 681-8600 or ceo@fpxnickel.com.

    On behalf of FPX Nickel Corp.

    "Martin Turenne"
    Martin Turenne, President, CEO and Director

    Forward-Looking Statements
    Certain of the statements made and information contained herein is considered "forward-looking information" within the meaning of applicable Canadian securities laws. These statements address future events and conditions and so involve inherent risks and uncertainties, as disclosed in the Company's periodic filings with Canadian securities regulators. Actual results could differ from those currently projected. The Company does not assume the obligation to update any forward-looking statement.

    Neither the TSX Venture Exchange nor its Regulation Services Provider accepts responsibility for the adequacy or accuracy of this release.

    SOURCE FPX Nickel Corp.

    For further information: Martin Turenne, President and CEO, at (604) 681-8600 or ceo@fpxnickel.com.