We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Gold/Mining/Energy : Zentek Ltd. -- Ignore unavailable to you. Want to Upgrade?


To: Stang11 who wrote (53767)10/8/2025 10:56:53 AM
From: roadguy5138 Recommendations

Recommended By
Candu
Canseco
Glorieux
Grapheneman
Nedski131

and 3 more members

  Read Replies (1) | Respond to of 53912
 
ChatGPT VERSION. (NOT FACT CHECKED)
Here’s a clear overview of the graphite brick testing process for the Albany Graphite Project and the approximate timeline based on standard industry procedures:



??

Testing Process for Nuclear-Grade Graphite Bricks





  1. Material Preparation
    • Mix synthetic graphite + ultra-high purity Albany graphite + coal-tar pitch.
    • Grind and blend to uniform particle size for pressing.
  2. Forming Bricks
    • Near-net-shape pressing to create solid shapes with preferred grain orientation (anisotropy).
    • Grain orientation is critical for thermal and mechanical performance in reactors.
  3. Carbonization / Baking
    • Pressed bricks are baked in a furnace at ~900–1200°C to carbonize the pitch binder.
    • Duration: 24–72 hours depending on brick size and furnace capacity.
  4. Impregnation (Optional)
    • To increase density and mechanical strength, some bricks are impregnated with pitch and re-baked.
    • Adds another 24–48 hours per cycle.
  5. Machining / Shaping
    • Bricks are cut or machined to final dimensions required for testing.
    • Ensures proper fit for characterization tests.
  6. Property Characterization (by AETC)
    • Density, porosity, and anisotropy measurements.
    • Mechanical strength: compressive, flexural, and tensile.
    • Thermal conductivity and expansion.
    • Boron content and other nuclear-relevant impurities measured (<2–6 ppm B).
    • Electrical resistivity and microstructure examined.

Time to Complete Test
Step

Typical Duration

Material prep & mixing

1 - 2 days

Pressing bricks

1 day

Carbonization / baking

1-3 days per cycle

Impregnation (if done)

1-2 days per cycle

Machining

1 day

Property characterization

2-5 days


Total estimated time: 1–3 weeks from initial mix to full characterization, depending on number of bricks and cycles.