G Mining Ventures Announces Formal Construction Decision for the Oko West Gold Project and Provides Project Development Update 						 						 						 					 				  				 			
  newswire.ca  			  				News provided by 				 					 						 							 								  							 						 						G Mining Ventures Corp 							 								 									 								 							 							 						 						 					 				 				Oct 23, 2025, 06:30 ET
  BROSSARD, QC, Oct. 23, 2025 /CNW/ - G Mining Ventures Corp. ("GMIN" or the "Corporation") (TSX: GMIN,  OTCQX:GMINF) is pleased to announce that its Board of Directors has  formally approved the commencement of full construction of its  100%-owned Oko West Gold Project ("Oko West" or the "Project")  in Guyana, following the completion of permitting and financing  milestones. Additionally, GMIN is excited to provide a progress update  on Project construction activities, including engineering, procurement  and early works activities. Unless otherwise stated, all dollar amounts  in this news release are expressed in U.S. dollars.
                                                                                                                                                                                                                                                                                                                      
                                                                                                                          Figure 1 - Earthwork Progress at Industrial Area (CNW Group/G Mining Ventures Corp)                                                                                                                                                  Figure 2 – Permanent Camp Construction (CNW Group/G Mining Ventures Corp)                                                                                                                                                  Figure 2 – Permanent Camp Construction (CNW Group/G Mining Ventures Corp)                                                                                                                                                  Figure 3 – Barge Landing Area (CNW Group/G Mining Ventures Corp)                                                                                                                                                                                                                                                                                                                                   - The Board of Directors has approved a positive construction  decision for the Oko West Gold Project, with an initial capital cost of  $973 million
 - Detailed engineering is 36% complete
 - Procurement and commitments for long-lead items are progressing,  with $334 million committed to date, representing 33% of the total  initial capital budget
 - Early works construction activities are advancing on schedule
                           "The official launch of construction at  Oko West marks a major milestone in GMIN's evolution into an  intermediate gold producer," said Louis-Pierre Gignac, President & Chief Executive Officer.  "With financing secured, we are advancing this fully permitted,  world-class project using the same disciplined, self-perform approach  that delivered Tocantinzinho safely, on time and on budget. Oko West  will build on that success as the next cornerstone of our growth  strategy, with first gold targeted for the second half of 2027".
                            Project Update (as of September 30, 2025) 
   Project Cost 
 
 - $110M has been spent, with an additional $46M in prepayments, for a total expenditure of $156M
 - Total commitments for project construction now stand at $334M  (including amounts spent), representing 33% of the total initial capital  cost estimate of $973M
   Safety Record & Workforce 
 
 - Total workforce of 710 of which 520 are employees and 190 are contractors
 - Over 80% of workforce are Guyanese nationals
 - 596,551 hours worked to date with one recordable incident to date, resulting in a Total Recordable Incident Rate (TRIFR) of 0.33
 - Completed a technical training program in partnership with the  Ministry of Labour of Guyana, benefiting 200 residents from region 7,  the administrative region hosting the Project.
   Sustainability & Permitting 
 
 - Permitting: Fully permitted under Environmental Permit No. 20230912-RGIGM, issued by the Environmental Protection Agency ("EPA") on August 29, 2025. The permit is valid for five years and authorizes both construction and operational activities
 - Licensing: The Mining License application has been submitted to the Guyana Geology and Mines Commission ("GGMC") and is expected to be issued in Q4 2025
 - Environmental and Social Management: The Corporation is advancing  the implementation of a comprehensive Environmental and Social  Management System ("ESMS") addressing biodiversity conservation, water quality, waste management, air and noise control
 - Community Engagement: A Community Development Committee has been  established in Region 7 to guide social investment initiatives in  education, healthcare, and infrastructure
   Engineering & Procurement 
 
 - Detailed Engineering: Approximately 36% complete
 - Procurement: Long-lead items have been ordered, securing pricing  for key equipment from reputable high-quality suppliers, including:    
- Power Plant: Supplied by Wärtsilä
 - Mining Equipment: Primary open pit and support equipment  from Komatsu, with the first mining shovel scheduled for commissioning  in Q4 2025
 - Processing Equipment: Grinding mills, gyratory crusher, apron  feeders, and pre-leach thickener from Metso. Gravity circuit, intensive  leach reactor, and gold room supplied by FLSmidth, with additional  mechanical packages sourced from other suppliers
 
    Early Works Construction 
 
 - Camp facility: Expansion of the exploration camp to a capacity of  425 beds; first two permanent dorms due in October; barge landing  satellite camp completed
 - Site clearing: 15 % completed
 - Access: 12 km external road operational, reducing travel time by three hours on return trip
 - Mass excavation: 100% complete at permanent camp; 93% at barge landing
 - Concrete: 2,815 m3 poured to date, 6% of the project
 - Tailings storage facility: Coffer dam completed; foundation prep and dam construction underway
   Approved Initial Capital Cost 
 
 - Board approved initial capex: $973M, in line with the Feasibility Study ("FS") estimate
 - Indirect costs: Increased due to additional construction equipment purchases
 - Pre-production revenue: 30,000 ounces ("oz") at $3,200/oz vs $2,500/oz in FS
 Contingency (incl. pre-production revenue): 8.8% 
                                        Table 1- Initial Capital Cost  
    |                           Initial Capital Cost Estimate   
     (US$ 000s)  
    |            Feasibility Study  
    |            Approved Initial CAPEX  
    |            Variance  
    |            % Variance  
    |                          Infrastructure 
    |           105,889 
    |           105,976 
    |           87 
    |           0.1 % 
    |                          Power & Electrical 
    |           110,797 
    |           108,553 
    |           (2,244) 
    |           -2.0 % 
    |                          Water Management 
    |           22,882 
    |           23,663 
    |           782 
    |           3.4 % 
    |                          Surface Operations 
    |           41,051 
    |           44,579 
    |           3,528 
    |           8.6 % 
    |                          Mining 
    |           104,078 
    |           105,216 
    |           1,138 
    |           1.1 % 
    |                          Process Plant 
    |           191,639 
    |           192,774 
    |           1,135 
    |           0.6 % 
    |                          Construction Indirect 
    |           134,534 
    |           146,102 
    |           11,568 
    |           8.6 % 
    |                          General Services & Owner's Costs 
    |           137,385 
    |           143,963 
    |           6,577 
    |           4.8 % 
    |                          Pre-Production 
    |           39,157 
    |           23,246 
    |           (15,912) 
    |           -40.6 % 
    |                          Contingency 
    |           84,962 
    |           78,598 
    |           (6,364) 
    |           -7.5 % 
    |                           Total  
    |            972,374  
    |            972,669  
    |            295  
    |            0.0 %  
    |                           Total excluding Pre-Production Revenue  
    |            1,041,389  
    |            1,061,071  
    |            19,682  
    |            1.9 %  
    |                           Pre-Production Revenue  
    |            (69,016)  
    |            (88,402)  
    |            (19,386)  
    |            28.1 %  
    |                                   About G Mining Ventures Corp.  
  G Mining  Ventures Corp. is a mining company engaged in the acquisition,  exploration and development of precious metal projects to capitalize on  the value uplift from successful mine development. GMIN is  well-positioned to grow into the next mid-tier precious metals producer  by leveraging strong access to capital and proven development expertise.  GMIN is currently anchored by the Tocantinzinho Mine in Brazil,  supported by the Gurupi Project in Brazil and the Oko West Project in  Guyana -- all with significant exploration upside and located in  mining-friendly jurisdictions. GMIN trades on the TSX under the symbol  "GMIN".
    Cautionary Statement on Forward-Looking Information  
   All  statements, other than statements of historical fact, contained in this  press release constitute "forward-looking information" and  "forward-looking statements" within the meaning of certain securities  laws and are based on expectations and projections as of the date of  this press release. Forward-looking statements contained in this press  release include, without limitation, those related to (i) the  construction and operation of Oko West creating about 1,270 jobs over  the life of mine; (ii) the initial equipment deliveries being expected  in Q3-2025 and enabling GMIN to start earthworks on site; (iii) and (iv)  in general,  the section entitled "About G Mining Ventures  Corp."; as well as the quoted comments of GMIN's President & Chief  Executive Officer. 
   Forward-looking statements are based  on expectations, estimates and projections as of the time of this press  release. Forward-looking statements are necessarily based upon a number  of estimates and assumptions that, while considered reasonable by the  Corporation as of the time of such statements, are inherently subject to  significant business, economic and competitive uncertainties and  contingencies. These estimates and assumptions may prove to be  incorrect. Such  assumptions include, without limitation, those  relating to the price of gold and currency exchange rates, and those  underlying the items listed in the above section entitled "About G  Mining Ventures Corp.". 
   Many of these uncertainties and  contingencies can directly or indirectly affect, and could cause, actual  results to differ materially from those expressed or implied in any  forward-looking statements. There can be no assurance that, notably but  without limitation, (i) a formal construction for Oko West will be made  in H2-2025, or at all; (ii) Oko West will progress in alignment with the  highest environmental and social standards; (iii) Guyana's regulatory  environment will ensure timely decision-making allowing GMIN to achieve  project milestones; (iv) Guyana will remain attractive for mining  investment; (v) Oko West will advance responsibly and on schedule; (vi)  GMIN will achieve its stated objectives for Oko West; or (vii) TZ and  Oko West will grow GMIN into the next intermediate producer, as future  events could differ materially from what is currently anticipated by the  Corporation. In addition, there can be no assurance that  Brazil and/or Guyana will remain mining friendly and prospective jurisdictions.  
   By  their very nature, forward-looking statements involve inherent risks  and uncertainties, both general and specific, and risks exist that  estimates, forecasts, projections and other forward-looking statements  will not be achieved or that assumptions do not reflect future  experience. Forward-looking statements are provided for the purpose of  providing information about management's expectations and plans relating  to the future. Readers are cautioned not to place undue reliance on  these forward-looking statements as a number of important risk factors  and future events could cause the actual outcomes to differ materially  from the beliefs, plans, objectives, expectations, anticipations,  estimates, assumptions and intentions expressed in such forward-looking  statements. All of the forward-looking statements made in this press  release are qualified by these cautionary statements and those made in  the Corporation's other filings with the securities regulators of Canada  including, but not limited to, the cautionary statements made in the  relevant sections of the Corporation's (i) Annual Information Form dated  March 27, 2025, for the financial year ended December 31, 2024, and  (ii) Management Discussion & Analysis. The Corporation cautions that  the foregoing list of factors that may affect future results is not  exhaustive, and new, unforeseeable risks may arise from time to time.  The Corporation disclaims any intention or obligation to update or  revise any forward-looking statements or to explain any material  difference between subsequent actual events and such forward-looking  statements, except to the extent required by applicable law. 
  SOURCE G Mining Ventures Corp
 
  For  further information on GMIN, please visit the website at www.gmin.gold  or contact: Jean-François Lemonde, Vice President, Investor  Relations, 514.299.4926, Jflemonde@gmin.gold
                                          |