We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Technology Stocks : TAVA Technologies (TAVA-NASDAQ) -- Ignore unavailable to you. Want to Upgrade?


To: Jack Zahran who wrote (16166)5/7/1998 2:41:00 AM
From: John Mansfield  Respond to of 31646
 
[UTILITIES] Voice of an insider

'Contributed by: Joseph Sgroi
Email: josephs@powerup.com.au

2 April 1998

I am extremely concerned about the possibility of severe electricity outages in the Year 2000.

Please allow me to convey my credentials on this topic:
I have been a computer professional for 24 years. I spent my first 20 years developing and managing
I.T. systems for a Power Utility, 7 years of which were directly involved in the development of software
for Power Stations in the area of Power Station Plant Management, Data Logging, Metering,
Maintenance Management Systems, LoadFlow analysis, Transient Stability and Short Circuit analysis. I
am currently the Year2000 Project Manager forfor a Police Service agency in Australia. This rather
unique mixture of roles has placed me in the rather uncomfortable position of being well aware of what
the Year 2000 Problem is all about and how it affects a Power Station.

Unfortunately I recall seeing many instances of 2-digit year fields in the Power Station environment.
This concerns me greatly. Data Logging systems feed directly into maintenance management systems
which are designed to shut down items of equipment when maintenance is not carried out. As you are
aware, this is done to safeguard worker safety and extend the life of the equipment. The sudden
incidence of "00" will cause many of these systems to FAIL.

The problem as I see it is as follows:

1.Many of these critical management systems cannot be decoupled. Equipment is inter-dependant
in a chain-like fashion.
2.Most Power Stations (in Australia) were built before 1980 using equipment and hardware from
1940 through to 1980.

3.Unlike most outages, where power can be re-directed from another line or Power Station, the
Year 2000 problem will occur in most if not ALL Power Stations at around THE SAME TIME.
This does not bear thinking about, as we must always have at least one Power Station on-line in
order to "kick start" the remaining Stations (termed "System Black").

In some countries gas-fired Power Stations are held in reserve for this purpose, but my
experience at these Stations is such that the equipment and systems are substantially the same as
in traditional fossil fuel Stations. Hence the probability of most or all Stations being affected at the
same time by the Y2K problem is VERY HIGH. This could lead to blackouts of weeks if not
months..... A truly catastrophic scenario with major impacts on society and our own families.

4.In Australia the awareness level of Y2K at Power Stations needs to be improved, although some
activity is present on the retail or distribution side.

5.Power Utilities around the world are proceeding through the process of corporatisation which is
diverting attention fromTechnical issues such as this.

The critical Systems likely to be affected in a Power Station are:

Control Systems
Data Logging and Metering Systems
Maintenance Management Systems
Safety Control Systems
Switching Systems

These critical systems all have both embedded components and firmware with date-related functions.

So why isn't there a sense of urgency about this? As I see it, the problem is one of awareness. It is fair
to say that the I.T. profession is more aware of the Y2K issue than any other profession. The reality is
that there has been very little I.T. involvement at the Power Station level. Most of the systems
operating at a Power Station are purpose-built systems supplied by non-I.T. firms, and the corporate I.T.
Department has had little or no involvement. As a result, Y2K awareness is not at the level it should be
with only 20 months to go.

We must thoroughly assess our level of risk at Power Stations IMMEDIATELY.

I hope I have made a contribution on this very important issue.

Yours sincerely,
Mr. Joseph Sgroi

millennia-bcs.com



To: Jack Zahran who wrote (16166)5/7/1998 2:46:00 AM
From: Jack Zahran  Respond to of 31646
 
Quote From the May 4, 1998 SmartReseller issue:
(Not posted on the web yet.)
YEAR 2000: Kill The Clock

"...Nuclear Regulatory Commission has had to replace the real-time clocks on hundreds of PCs with Y2K-compliant clock chips. Last year a batch of 600 new PCs flunked the agencies Y2K test...

"One difficulty users and resellers are having in fixing the PC compliance problem is the dearth of motherboards that incorporate Y2K-ready clocks...

"In the meantime, resellers who have identified the clock problem have a limited set of software fixes for the hardware problem." -end of article

The article also mentioned that Dallas Semiconductor Corp. (http://www.dalsemi.com/) is the only company manufacturing Y2K-compliant real-time clocks. Currently Asus(a leading motherboard manufacturer, asus.com is using their clock and EGCS Inc. is evaluating it (http://www.ecsusa.com/)