I played with a few numbers:
The following is just mumble jumble but was done for just the speculation side of Nuinsco!
Would be nice kinda sorta!
Try to follow my numbers:
Ore Reserves Lac Rocher Nickel Deposit 33,600,000 Tonnes Assumptions made for Area of Influence Strike 400 Meters Life of Mine 12.0 Yrs Width 200 Meters Depth 150 Meters S.G. 2.8 Mine Size/Production Strip Ratio 1.0 : 1.80 Operating Days/Year 350 250 days/year mine; 350 days per year mill Per Day Per Year Ore Tonnes/Day 11,200 2,800,000 Waste Tonnes/Day 20,200 5,050,000 Total Tonnes/Day 31,400 7,850,000 Personnel Requirements Mine 140 Mill 100 Service 70 Admin./Technical 40 Total Personnel 350 Power Requirements Peak Load in kW 21,000 Power Consumption (kWh/day) 376,400 Mine Site Ultimate Pit Limits (acres) 190 Infrastructure (acres) 5 Total Acres Cleared 195 Ore Removal Drilled Tonnes/Day (2 drills - 7.875") 46,028 31,400 Shovel Size (cubic yards) 10 Number of Shovels Required 4 Truck Size 120 Number of Trucks Required 10 Open Pit Repair Shop (sq. feet) 22,700 Capital Costs Clearing of Open Pit Area $180,000 Pit Soil Stripping $608,000 Waste Stripping Drilling Equipment $1,650,000 Loading Equipment $12,880,000 Haulage Equipment $15,170,000 Pit Maintenance Facilities $3,980,000 Communications/electrical Distribution $990,000 Clearing for Concentrator/Crushing Plant/Service Facilities $10,000 Clearing for access roads (5 Kilometers) $870,000 Infrastructure Soil Stripping $40,000 Infrastructure Excavation (cubic meters) 6,700 Mass Excavation for Infrastructure $1,340,000 Detailed Infrastructure Excavation (cubic meters) 670 Infrastructure Excavation (cubic meters) 3,350 Excavation and fill Compaction $70,000 Concrete Foundations $3,175,000 Concentrator Building $7,260,000 Gyratory Crusher $278,000 Primary Crushing Plant $10,250,000 Fine Ore Crushing Plant $12,300,000 Grinding Mills & Fine Storage Bins $12,774,000 Process Capital Costs (Purchase & Installation) $8,093,000 Initial Tailing Storage $2,646,000 Water Supply System $3,765,000 Surface Distribution System $3,300,000 Diesel Electrical Plant $17,216,000 Plant Office Area 4,300 Construction of Plant Office $288,800 Surface Plant Maintenance Shop $255,000 Changehouse $303,000 Warehouse $240,000 Miscellaneous Surface Facilities $1,059,000 Contingency @ 10% $12,099,080 Total $133,089,880 Mine Project Overhead Costs Engineering $7,262,000 General Site $6,355,000 Project Supervision $5,684,000 Administration $4,736,000 Contingency @ 10% $2,403,700 Total $24,037,000 Total Capital & Project Overhead Costs $157,126,880 Open Pit Operating Costs Per Day Per Year Per Tonne Ore Drilling $3,000 $750,000 $0.27 Blasting $5,000 $1,250,000 $0.45 Loading $4,000 $1,000,000 $0.36 Haulage $26,000 $6,500,000 $2.32 General Services $10,000 $2,500,000 $0.89 Total $48,000 $12,000,000 $4.29 Concentrator & Services Operating Costs Crushing $2,200 $770,000 $0.28 Fine Crushing $3,400 $1,190,000 $0.43 Grinding $8,600 $3,010,000 $1.08 Processing $26,000 $9,100,000 $3.25 Tailings $1,600 $560,000 $0.20 Assaying $2,300 $805,000 $0.29 Supervision, maintenance, & general other $11,000 $3,850,000 $1.38 Electrical Power $26,900 $9,415,000 $3.36 Surface Services $11,000 $3,850,000 $1.38 Administration & Technical Staff $9,000 $3,150,000 $1.13 Total $102,000 $35,700,000 $12.75 Total Operating Costs $150,000 $47,700,000 Operating Costs per Tonne Ore $17.04 Gross Metal Value/Tonne Value/Tonne Nickel Grade 1.59% $68.70 Copper Grade 0.57% $9.42 Ni. Equiv. Grade 1.81% $78.12 Profit/tonne ore $61.09 Profit as Per Assumed Deposit Size: $2,052,490,182 Total Cap Ex. $157,126,880 NPV @10% $916,629,773 |