Good write up on TAVA Now I will address what one company (Tava) is finding as they work on the non-IT assessments of a number of large businesses. Bill Heerman of Tava's Denver office presented the session in Chicago. Mr. Heerman reported on four of the companies his company was helping. They are working with a major food processing company, a major automaker, a major soft drink company and a major pharmaceutical manufacturer. Because of contract agreements, Mr. Heerman couldn't name the companies. Mr. Heerman began by using the illustration of an iceberg and comparing the non-IT area of manufacturing to be like the big (underwater) part of the iceberg -- an apt metaphor for titanic times. He gave a couple of examples of IT personnel at companies saying, "That's not my job," when asked to help with embedded systems issues. Then he made the comment that while traditional IT counts the money, it is non-IT that MAKES the money. Finding the embedded systems is everyone's job because everyone's job depends on finding and fixing the systems.
Brainstorm devoted several days of the Chicago conference to the non-IT aspects of the year 2000 problem. I am not going to attempt to cover the methodology and tools used for non-IT assessment and remediation. If you want to know how they do it, just call some of the vendors or go to the next Brainstorm conference in New York (Aug. 31-Sept. 2) What I will cover in this issue are the numbers that Mr. Heerman released on the overall difficulty of each project, what they think it will cost and how long they think it will take for four different major companies.
------------ Case Study #1: The pharmaceutical company
The pharmaceutical company has global operations in 39 countries. In addition to their manufacturing systems, they have laboratory systems, along with their facility systems (and their external dependencies). One fully integrated complex was done. 4,457 items were inventoried and of these 2,618 were unique. 392 were in the Lab, 980 were in the facility, 837 were in manufacturing, and 409 were found in external relations.
The results were that 18% of the more than 4000 items were found to be non-compliant and 17% would cause a plant shutdown or would affect production.
In the lab, 18% of the hardware was non-compliant and 27% of the software needed to be fixed. 36% of the custom code was non-compliant. 8% of the suppliers of these non-compliant systems were no longer in business and 11% of the suppliers would not supply an upgrade except with the purchase of a new model.
Of the manufacturing systems, 16% of the hardware and 22% of the software was non-compliant. 41% of the custom code wasn't compliant either. 9% of the suppliers were out of business and 18% would not provide upgrades except through new models.
In the company's facilities, 18% of the hardware and 33% of the software was non-compliant. 29% of the custom code was non-compliant. 11% of the suppliers were no longer in business and 21% wouldn't upgrade except for new models.
In the external dependencies, 12% of the hardware, 25% of the software, and 27% of the custom code was non-compliant. 5% of the suppliers were out of business and 9% wouldn't upgrade except through new models.
The chance of these facilities failing was 70% for the lab, 80% for manufacturing and facilities, and 90% for the external dependencies. This means that without any remediation at all, total plant failure is a very good bet. It was estimated that seven out of nine manufacturing lines would stop running within the first 3-4 days, and the network and telecommunications equipment wouldn't work. Security systems would admit anyone with any credit card and the in-plant power substation would fail along with municipal water.
For just one plant, the inventory is expected to take eight weeks and the analysis is expected to take five weeks. Risk assessment is expected to take two weeks. Inventory and analysis would cost $487,000. The estimated time to fix is 43 weeks and the estimated cost is $1,200,000. For all 125 plants, the inventory and analysis would take 39 weeks and the cost would be $11.5 million. The fix would take 31 weeks and the cost was estimated at 54.8 million.
------------ Case Study #2: The major beverage company
The major beverage company has global operations that include 47 plants in 21 countries. The company has
manufacturing systems and laboratory systems along with facility systems. There is also a lot of Eastern European and Russian equipment in the plants. Nine plants were done in a pilot project. 3,819 items were inventoried and 894 were unique. 210 were in the lab, 304 were in facilities and 380 were in manufacturing. 24% were non-compliant and 28% of them would affect production.
In the lab, 34 % of the hardware, 26% of the software and 39% of the custom code was non-compliant. 16% of the suppliers were out of business and 34% of the suppliers of non-compliant products did not offer upgrades except through new models. 35% of the equipment would have to be replaced.
In manufacturing, 26% of the hardware, 23% of the software and 33% of the custom code wasn't compliant. 15% of the suppliers were no longer in business and 21% offered no upgrades except for new equipment.
In the facilities, 9% of the hardware and 6% of the software was not compliant. There was no custom code. 19% of the suppliers were out of business but 40% of the technology was old and manually operated.
The inventory and assessment took 20 weeks and cost $893,000. Time to fix was estimated at 35 weeks and the cost at $2.9 million.
For all 47 plants, the inventory and assessment was estimated to take 25 weeks and cost $4.9 million with the fix taking 29 weeks and the cost estimated to be $23.4 million.
------------ Case Study #3: A major automotive manufacturer
The major automotive manufacturer has global operations with 162 plants in 41 countries. Two plants were done in a pilot project. 1,389 items were inventoried with 435 of them being unique. 131 items were in the facility, 254 in manufacturing and 50 in external dependencies. 16% were found to be non-compliant and 6% could cause a serious plant shutdown.
In the manufacturing systems, 11% of the hardware, 19% of the software and 37% of the custom code was non-compliant, but this time all the suppliers were still in business. 18% of the suppliers would not provide an upgrade except through a new model.
In the facilities, 17% of the hardware, 19% of the software, and 42% of the custom code was non-compliant. 7% of the suppliers were no longer in business and 21% would not provide an upgrade except through a new model.
The greatest threat to this client was the supply chain with more than 60,000 suppliers. Of these, 7,500 suppliers are critical to the manufacturing process. 30 suppliers were investigated and only 6 had active and defined year 2000 programs. The other 24 maintained that they were already compliant. After testing, 46% of these were projected as non-compliant.
The inventory and analysis of the two plants took nine weeks and cost $221,000. The fix was estimated to take 12 weeks and cost $1.1 million. For all 162 plants, the inventory and analysis was estimated to take 31 weeks and cost $13.6 million, with the fix taking 58 weeks and costing $72.2 million. The risk assessment for the plant projected that 3 out of 4 of the manufacturing lines would stop running in the first 2 days. The networks and communications would fail, and the security systems would refuse to admit anyone. One of the two power substations would fail and the city's sewer removal system would fail and could not be upgraded.
------------ Case Study #4: The petroleum company
The final large client was a global petroleum company with 18 plants all located in the United States. The systems identified were quality systems, manufacturing systems and
energy management systems. The pilot project was an inventory and assessment of a catalytic cracker and the co-generation plant. The tie-on system with the local grid was also included.
1,035 items were inventoried and 514 of these were unique. 365 were in manufacturing and 149 in external dependencies. 21% were not compliant and 6% would cause serious plant shutdowns or affect production negatively.
The results for the manufacturing systems were that 11% of the hardware, 14% of the software and 23% of the custom code was non-compliant. 2% of the suppliers were no longer in business and 12% of the suppliers would not supply an upgrade except through purchase of new models.
For the quality systems, 24% of the hardware, 29% of the software and 29% of the custom code was found to be non-compliant. All suppliers were still in business but 16% would not provide upgrades except through new models. The risk of failure was put at 60%.
For the co-generation plant's results, 19% of the hardware, 36% of the software, and 24% of the custom code wasn't compliant. 13% of the products were no longer made. In this case, the energy management system tied into the local grid that was non-compliant and couldn't be upgraded. Some of the more interesting findings were that the catalytic
cracker would fail and the refinery could no longer make gasoline. One of the more troublesome findings was that the analyzers would continue to work but would send erroneous data. The proprietary networks from the control systems to the analyzers would fail. The inventory and analysis would take 7 weeks and cost $122,000. The conversion for two units would take an estimated 15 weeks and cost $760,000.
------------ In Summary
In an overview of all these facilities, problems were found in the sensors & analyzers, lab equipment, programmable Control Systems, embedded systems, SCADA systems (Supervisory Control And Data Acquisition), distributed control systems, human-to-machine-interfaces (HMI's), networks, computers, third party applications, and Operating Systems.
Mr. Heerman also noted that they had found that some of the vendor compliance statements were incorrect. Some pieces of equipment the vendor had claimed to be compliant had failed. One piece of equipment successfully made the January 1, 2000 transition and was allowed to continue. Just over a month later, when checked again, the date on the equipment was January 34! This points out the need for continued testing, especially at the system level.
Mr. Heerman also indicated that Tava has found that the single most important thing that can make a year 2000 project successful is the degree to which executive management is involved.
The projected risk levels for failure of all the units of these companies was between 60% and 90% if the non-IT parts of the business were not found and fixed. I think the main difference between the Cargill and Tava plans is the level of thoroughness in the inventory and assessment phase.
Also, a company like Tava has access to a large database of compliant and non-compliant devices that might not be available to individual companies.
An open question is the same one I posed in my coverage of Cargill's approach. Is 90% assessment and inventory with work-arounds for the rest good enough? One person wrote me and said it was similar to a house losing 10% of its nails. I agreed with him because I used to make houses. If a house loses 10% of its nails over the entire house, it won't fall down. Other than some more squeaks, probably no one would notice any difference. That's because most houses are overbuilt by a factor of at least 50%. But what if the 10% of nails were all in one corner of the house, or just in the floor joists? Then the house would fall down, or become uninhabitable. Some companies will fail because of this. For them, 90% won't be good enough because the nails they lost were the ones that held the place together.
Usually, one nail doesn't make that much difference. But sometimes it does. I'm reminded of the quote: "For want of a nail, the shoe was lost. For want of a shoe, the horse was lost. For want of a horse, the rider was lost. For want of a rider, the battle was lost."
It will be really interesting to see what ultimately comes out of this.
Best practices, Jon Huntress jon@year2000.com
The Year 2000 Information Center |